START Launch discussion - 10/14
Wendy, Scott, Hari, David B, Dawn, Kesha (Roger sick, Adriene meeting with Len, D. Rich out sick)
Adriene - work weekends, need to negotiate Nancy's list of reqs. - enhancements?
ITS Website
In Development - Fruition billing? - Bill/Adriene
- Financial Approval Workflow (Fruition) - awaiting notifications - me
- ITS Backup Service (everything except user delete) - Fruition done by Friday 10/18
In Defect Cycle
- Telephone Services
- Mobile Device Change
- Pagers?
In Testing
- Initial testing
- Back-up user delete
- Ethernet ? - HARI - maybe 1.
- Defect Testing
- UAT
- Pagers (awaiting defects)
- Ethernet (awaiting defects)
- Regression (2 weeks after code freeze)
- Load Testing
Training
- Quick Guides
- Captivate Video - can't begin until
- Pilot Training
- Training
Assumptions - Nancy's initial UAT wishlist is NOT included.
Launch on Nov. 22
Code freeze - Nov 13
Training begins - Nov 11
UAT fixes - Nov 7-12
Scott Captivate - Nov 6
Nancy's UAT - Nov 6
Pilot Training - Nov 4
Kesha UAT - Oct 30 (Nov 1, 2-3, Religious holiday for Kesha) - assumption - Kesha is 100%.
Logie UAT - Oct 31
(Load testing would need to be done here - need to secure resource from Jason Schuff, based on plan)
Defect cycle with all forms & financial approval complete - Oct 29
ITS website work completed - Oct 29 (need resource help from Lec/Lisa)
Oct 14-Oct 29 to finish defects, development and testing - without Nancy scope = 2 weeks plus weekends
(assumptions - START needs to trump CMDB esp. for Hari, David needs to be removed from on-call, D. Rich at 100%)
David - out (10/18-21)