Week of 2013-05-21

General Info

Regularly scheduled weekly status for START replacement.

Please let Christine know if you plan to call in.

Call-In Info

  1. Dial 6-5777, (203) 436-5777 or (855) 925-3266.
  2. Enter Meeting ID 60612 and #.
  3. Speak your name, then enter #.

Roll Call

Name

Role

Present

Christine Costantino

PM

(tick)

Kesha Patel

BA

(tick)

Barbara Manville

SME / BA

(tick)

David Logie

BA

(error)

David Backeberg

Tech Lead

(tick)

Hari Adusumilli

Test Lead

(tick)

Wendy Battles

CM

(tick)

Bob Liu

ITS Web Dev

(error)

Roger Kennedy

Portfolio Manager

(tick)

Chris Kilbourne

Web Functional Lead/Sponsor

(error)

Jeff Euben

CTS Voice

(error) (optional)

Adriene Radcliffe

Sponsor

(error) (optional)

Agenda

Please come to the meeting on time & prepared

  1. Review Action Items from last week
  2. Review Project Plan deliverables
  3. Obstacles & Risks

Discussion

* Roger led the discussion with the project plan, Christine took notes.

Review of Action Items

  • Christine - Will update the mockups for the Focus Groups and schedule the XTRAIN meeting with Judy, Roger, and Jay.
  • Wendy - Finish financial approval notifications this week, then send to Janet for review

Review of Project Plan Deliverables

Analyze Phase (As-Is)

  • Display responsibilities (Christine) - 100% Received response from IAM folks. This will be available via Sailpoint once the various systems are connected to Sailpoint in the future.

Design Phase (To-be)

  • Financial notification (Wendy) - 20%
  • Travel Orbitz - travel arranger designation, policy approvers, two others?
  • SciQuest, Xpressshipping - next for Barbara
  • People Lists - need to change dates with Barbara
  • Mobile Device - 5% Kesha
  • Schedule XTRAIN meeting - Christine next week
  • TMS - set-up, need sign-off from Julie Grant
  • Training approach due 5/14
  • Training plan - June
  • Generate NetID PIN - David Loge

Build Phase

  • ESS requirements for 5/15 - complete. Christine is meeting with Mark Kovacs and Jeff Capuano re: new incident form.
  • PTAEO validator (David) - 100%
  • Copy PTAEO - 95%
  • Financial approval (David) - UAT in progress - defects to Fruition - 85%
  • Mockup for Telephone sets & lines - 100%
  • Pagers - UAT found defects, send to Fruition
  • Order Guides - fix dates

Test Phase

  • Pagers (Hari) - 80%, pending financial approval workflow
  • PTAEO test cases 60%
  • Financial Approval - pending

Develop cut-over plan

Obstacles & Risks

Release Status (START items labeled purple)

text to show when browser does not support iframes