Week of 2013-04-30
General Info
Regularly scheduled weekly status for START replacement.
Please let Christine know if you plan to call in.
Call-In Info
- Dial 6-5777, (203) 436-5777 or (855) 925-3266.
- Enter Meeting ID 60612 and #.
- Speak your name, then enter #.
Roll Call
Name |
Role |
Present |
---|---|---|
Christine Costantino |
PM |
|
Kesha Patel |
BA |
|
Barbara Manville |
SME / BA |
|
David Logie |
BA |
|
David Backeberg |
Tech Lead |
|
Hari Adusumilli |
Test Lead |
|
Wendy Battles |
CM |
|
Bob Liu |
ITS Web Dev |
|
Roger Kennedy |
Portfolio Manager |
|
Jay Johnson |
IAM CM |
|
Jeff Euben |
CTS Voice |
(optional) |
Adriene Radcliffe |
Sponsor |
(optional) |
Jane Livingston |
Sponsor |
(optional) |
Agenda
Please come to the meeting on time & prepared
- Introduction of David Logie
- Review Action Items from last week
- Review Project Plan deliverables
- Obstacles & Risks
Discussion
* Roger led the discussion, Christine took notes.
Introduction of David Logie
Review of Action Items
- Christine - Update Work Plan and Risk Log - Reschedule XTRAIN meeting (include Roger), schedule meeting with Client Accounts and David Logie
- Wendy - Finish financial approval notifications with Janet (Friday 5/3 w/Janet), Schedule focus groups all but one, need room (May 13, central side), need to set-up TMS and send communication
- Dave - Financial Approval workflow - UAT + defects, ESS work in queue - done
Review of Project Plan Deliverables
Analyze Phase (As-Is)
- Display responsibilities (Christine) - 50% Awaiting response from IAM folks.
Design Phase (To-be)
- Financial notification (Wendy) - 5/3
- Telephone sets and lines (Kesha) - 100%
- People lists request (Barb) - Travel Arranger req document - meeting with Travel folks
- Focus groups (Wendy) - all but one finished - change to 5/24
- Generate NetID PIN - David Loge
Build Phase
- ESS requirements for 5/15
- PTAEO validator (David) - 2 more reqs: multiple ptaeos, copy ptaeos - PTAEO sprinkles
- Financial approval (David) - Frution is working on defects
- Ref table for Ethernet (David) - 75% passed QA, advance to prod - to be released
- SciQuest API (David) - Rob Bores (service owner), Kahzi (developer?)
- Pagers (David) - 100%
- Mockup for Telephone sets & lines - 5% due 5/3
- Mobile Device - fix dates
- Fix CCB date
- Ethernet - Fruition 5/10
- Order Guides - fix dates
- Web - Incidents 100%, May Cart 100%
Test Phase
- Pagers (Hari) - 80%, pending financial approval workflow
- PTAEO test cases - meeting with Igor today
Develop cut-over plan
Obstacles & Risks
- David - YUV data - Igor today!
- 2 weeks - ServiceNow conference, David release
Action Items
Release Status (START items labeled purple)
text to show when browser does not support iframes