2012-015-03 UAT Stand-up

General Info

Documents

Roll Call

2011/02/27 9:30pm EST

Name

Org

Present

Roseann Adams

Yale

(tick)

Mike Okrent

Yale

(tick)

Barbara Manville

Yale

(tick)

Bill West

Yale

No

Chloe Turnbull

Yale

(tick)

Vamshi

Yale

(tick)

Mary Kay Kaminski

Yale

(tick)

Discussion

Agenda

Please come to the meeting prepared with answers, even if it's to report nothing, no progress, or no obstacles.

  • What did you do yesterday?
  • What are you doing today?
  • What obstacles are slowing/stopping progress?

Answers

Vamshi

  •  
  •  
  • 3/13: 
  • Roseann sent email to Derek and Leanne regarding problem defects; were some of the problem defects addressed yet? I saw that you had problem defects yesterday. 
  •  Will we have FP access to HPQC today?  Can we train Derek, Leanne and Suneetha?  Can set up time to orient FP to our HPQC environment.
  • Still have not seen problem defect fixes. -  get with Derek, Leanne this during todays tech stand up
  • Retesting
  • Send out defect report
  • New test report
  • Email notification issue will not be fixed till clone on Wed

Mary-Kay

  • Deployment communication spreadsheet - Need to communicate the contract operation process - work with Barb, Ade and Jeff (Jeff needs to write SOP)
  •  
  •  
  • 3/13
  • Is coach list final yet?  yes (Have contractors been added?  Why would contractors be coaches?  Are the contractors going to be invited to training? only added to training)
    • Communication plan for deployment (What folks can expect?  per our discussion yesterday; finishing tickets in HPSM, rekeying ticket, problems, changes, attachments)
    • Finalizing plan on exit strategy.  Communicate when and who will be deployed. 
  •  obstacle - Knowledge management lunch & learn
  • Vetting takes a lot of time
  •  
  •  
  • MMN article for SMS rebranding & quality mgmt program
  • Demo of SN for SOM, very interested in some solution for their org
  • Met with Chloe refining assignment unit work to compare all folks including contractors; Work with Jim McKay
  • Working with Lori on KM lunch & learn (what we will and will not do)
  • March 27 demo ServiceNow install
  • Updating coach list

Roseann:

  •  
  •  
  • Spoke to Derek, can get the "when" for required fields in UAT, Chloe looked at HPSM, the when of required fields not in prior requirements
  •  Too many meetings
  • Send note about problem defects to Leanne
  • Speak to Jeff regarding the "DSP Visit" thing.....
  •  
  • Started creation of new ITSM roadmap post-go live work streams and future projects
  • Finalize required fields for incident, problem, change
  • Today, update schedule with training dates Mike provided
  • Status reporting
  • Ed and Patrick on warranty and VSA SOW 
  • Action: escalate problem defect fixes

Mike:

  • Will need to train contacts and DSP assignment - work with Barb
  •  
  •  
  •  Please provide status on training tasks per the hard copy I provided last week
  • Where are we on the Change SOW, signed off, double check to see if we have the right dates in the schedule. 
  • Is the incident/request training complete?  Can we leverage for UAT? 
  • Progress on problem; did you get with Lou on the problem scenarios? 
  • Coach communication - sent out yet?   Dependent in MK completing coach list??? 
    • Managers of groups, working on communication to be sent out this week and in MMN next week (per MK)
  • Worked on training quick guide for SN, still soliciting input. 
  • Working on incident materials,final review complete, final materials to be complete on Tuesday, Mar 20
  • Working with Dawn and Lou on problem, Dawn provided examples
    • Can we use the training material for UAT for Group UAT not process owner UAT, can give Process owners a draft
  • Not working on Knowledge yet
  •  

Provide cost of quick guide 500 at $3500.00  

  • Got FP incident & request training material (significantly improved), sent out to Dawn & David
  • Working on training aid (socializing and finalizing design)
  • Meeting with Lou and Paul and Ian to finalize what we want on the change training
  • Illness (Mike has a cold)
  • Coach communication done, waiting for final list
  •  Has not received problem scenarios

Barbara:

  •  
  •  
  •  
  •  
  • DSP billing; assignment group, contract, DSP team work, mtg with Jeff to discuss
  • Do we need request type of "DSP Visit"  - impact to

Chloe:

  •  
  •  
  •  
  •  
  •  
  •  
  • Follow up with FP on new call requirements -
  • Revisit decision on ESS?
  • Add requirements, communicate to FP re: self service page - what to hide from itil users
  • Email intake - can we compartmentalize email intake per group going live? 
  • Deployment meeting - start spreadsheet on SharePoint? 
  •  
  • Yesterday; sent out invites to process owners and full on uat
  • Will not attend stand ups next week, caledar full
  • Will need help on
    • getting a lot of questions on requirements that need to get nailed down (Vamshi, FP)
    • Options for UAT scripts
      • Chloe has asked process owners to bring examples
      • The problem is the group uat testers
      • Chloe has the scenarios, need to write test scipts in HPQC
      • Set up meeting, on Wed or Thur Vamshi, Barb, Ro
  •  
  • Sent final assignment units and assignees to Bill to include on Monday's clone
  • Send out commuication to process owners for UAT
  • Send out commuication to general folks for UAT
  • New call completed
  • Decision not to include ESS to clients
  • Chloe to log decision on ESS
  • Tomorrow - meet with Roseann on MS Project
  • Email intake addresses - we cannot put email addresses into the system until we go live
    • Bill is putting together alias' to help test
  • Chloe scheduled meeting - for one list of things we have have to do for deployment, including DJ

Bill:

  • Go live - excel spreadsheet, Bill to put on SharePoint - MK to put in right place
  •  
  • Add list of deployment tasks to spreadsheet
  • Do we have to change email alias' the Tuesday night before we go live for each group? takes overnight for email alias
  •  
  •  

Backlog

Meetings

Actions

  • Roseann will connect w/ testing staff and process owners to back fill for Jeff
  • Tech team will review defects list and requirements as well
  • Everyone needs to look at and provide feedback for the schedule options sent by Roseann