Work Priority/Sequence

See: 2013-04-29 - Process Owners Operational

Release Status

text to show when browser does not support iframes

Roll Call

Name

Org

Present

Bill West

Yale Dev

(tick)

David Backeberg

Yale Dev

(tick)

Chloe Turnbull

Yale BA

(error)

Hari Adusumilli

Yale QA

(tick)

Tim Nichols

Yale

(tick)

Christine Costantino

Yale

(error)

Ricardo Chavira

Yale

(tick)

Kesha Patel

Yale

(tick)

Agenda

Please come to the meeting on time & prepared

  • If you don't have a status change, that's OK! Just say so.
  • What did you do yesterday?
  • What are you doing next? (like, within the next day or two? Break "ongoing" tasks into pieces).
  • What obstacles are slowing/stopping progress?

Discussion

Bill:

  • Done:
    • reload remaining items which are ready for test into the test instance
    • finish LOE RTS estimates in HPQC
    • follow up on last-minute R798 changes
    • DSP Contract issue INC0166384
    • R510 fixes
  • Next:
    • resolve issue with R671
    • Release 3 of CMDB (SNMP)
    • Send R936 to FRU
  • Obstacles:
  • Backlog:
    • Request Process functional doc draft
    • schedule a SN KB hackathon

David:

  • Done:
    • R934 sent to FP
    • large portion of FP backlog to FP (incl. mobile device add)
  • Next:
    • relabel PTAEO field (R934)
  • Obstacles:
  • Backlog:

Kesha:

  • Done:
  • Next:
    • mobile device change requirement analysis (R# TBD)
  • Obstacles:

Ricardo:

  • Done:
    • talked w/ Bill re: data source access
  • Next:
  • Obstacles:

Tim:

  • Done:
    • QB app extensions done
  • Next:
    • speak w/ Chloe on Mon re: CMDB UAT
    • connect w/ Bill to get access to the Applications Data Source
  • Updates:
    • schedule updated
    • working on plans for data checking
    • Jun 7th go-live for release 1

Hari:

  • Done:
    • finished regression for 7/5 release
    • worked on testing R855 R931 R899
  • Next:
    • Test: R715
    • Test: R586 R619 R620 R621
  • Obstacles:
  • Backlog:

Chloe:

  • Done:
    • checked w/ R723 waiting on Cheryl & Lou
    • tested R620, R621, R510
  • Next:
    • test R586
    • test R619
    • check again w/ R723 waiting on Cheryl & Lou
    • process owner meeting notes
    • Change Redesign
  • Obstacles:
  • Backlog:

Ricardo:

  • Done:
  • Next:
    • R654 get Mark signoff for new incident form
  • Obstacles:
  • Backlog:

Christine:

  • Done:
    • new incident form on hold, sent to RTS queue for resequencing
  • Next:
  • Obstacles:
  • Backlog:

Past Meetings