2013-10-21 - Process Owners Operational
AGENDA
- Discuss issues (if any) from the last release
- Review the current work stream
- Discuss any new work to be added to the work stream
- Discuss prioritization of work stream
- Discuss open Action Items
ROLL CALL
Name | Representing | Attended | Alternate Attendee |
---|---|---|---|
Adusumilli, Hari | ServiceNow QA |
| |
Boeher, Cheryl | Problem Process |
| |
Chavira, Ricardo | Service Catalog/Request Process | Soren Sonson | |
Ortale, Dorothy | Knowledge Process |
| |
Kovacs, Mark | Incident Process |
| |
Smith, Rick | Metrics/CSI Process |
| |
Tiseo, Lou | Change Process | ||
Turnbull, Chloe | ServiceNow Team Lead |
| |
Valdes, Julio | Configuration Management Process | Tim Nichols | |
West, William | ServiceNow DEV |
| |
Costantino, Christine | START Replacement Project Manager |
| |
Nichols, Tim | CMDB Project Manager |
| |
Radcliffe, Adriene | ITSM Director |
| |
Sonson, Soren | Request Process |
|
MEETING NOTES
DISCUSSION
- Discussion of last week's SN release.
- Post release it's been discovered that individuals are unable to sort by the database in affected component field. A defect will be logged for this.
- Post release it's been discovered that the provider services are not mapping to Business Services. A defect will be logged for this.
- Staffing updates
- We have a new BA starting, David Rich, who has been working with our testing team. His first order of business will be working on the Change process. He will need to transition his testing responsibilities to another person from the Testing team.
- We are interviewing a person from Fruition to be located at Yale to work on development. This person's first order of business will be working on the Change process and some RTS defects.
- Project Updates
- CMDB
- Work scheduled out through end of the year
- Bill is currently working on Release 5 and 6 (network and subnet devices; enabling modifications to businesses services within ServiceNow).
- START
- End of this week will be a go-no on the scheduled release date of 11/22
- Adriene will ask Bill to do a level of effort assessment on one defect that would apply to all Request forms. Depending on the level of effort this may impact a release date.
- CMDB
- John Pagliuca is asking for R-765 (currently #9 on the priority list) to be moved up as it is affecting their ability to serve their clients in a timely manner.
- This will be moved up to the top of the list.
- Jeff Capuano has three items he would like to add as a priority. He needs to onboard three CTS groups; Film Study Center, Photo & Design and Classroom Technology & Event Services. This will need BA work along with development work.
- The new BA starting can work on this. We would also like to leverage the new Service Improvement Specialist starting within CTS soon.
- We will Process Owners would like to see priority by project and a breakdown of a person's percentage for each work stream
RTS PRIORITIES AND STAFFING PERCENTAGES
Business Analysis: Dave Rich 100% (after transition from testing to John Schmidt)
Development:: Bill West 50%
Testing: John Schmidt 50%
Priority | Item # | Description | BA Level of Effort | BA - % Complete | DEV Level of Effort | DEV - % Complete | TEST Level of Effort | TEST - % Complete | Process Owner | Scheduled Release |
---|---|---|---|---|---|---|---|---|---|---|
1 | R-765 | Re-Work the DSP Contracts to accurately reflect who is supported to the DSP Teams and who is supported by FAS-IT | Hours | Completed 9/16/2013 | 9/16/2013 | |||||
2 | R-821 | Change - Update Change process and update ServiceNow to reflect those process changes. This will be done as part of the CMDB project. | Weeks | 50% |
|
| ||||
3 | R-813 | Allow clients to request assistance online via chat | Hours | Completed 5/31/2013 | 5/31/2013 |
| ||||
4 | R-630 | Knowledge - Define a process for letting support teams know when there is new KB article that may be of interest to them. | Hours | 0% |
|
| ||||
5 | D-556 | Users can save/resolve/close tickets without filling out all of the required fields | Hours | Completed 7/15/2013 | 7/15/2013 |
| ||||
6 | R-896 | Determine a way to let Len Peters and Leadership know when a P1 Incident has been created (this replaces the old E-795) | Days | Completed 8/14/2013 | 8/14/2013 |
| ||||
7 | R-938 | New Service Request: Software Library Addition or Change (Fruition) | Hours | Completed 7/15/2013 | 7/15/2013 |
| ||||
8 | R-901 | Allow Request forms to be visible and fill-able by persons outside Yale | Days | 30% (Estimated) | 9/9/2013 |
| ||||
9 | R-767 | Implement New Ticket Feature in the DEV or TEST instance | Weeks | Unsure | 5/31/2013 |
| ||||
10 | R-1094 | Notification for Knowledge Records that are about to expire | Hours | 50% | ||||||
11 | R-978 | Problem Process redesign | Weeks | 0% |
|
|
CMDB PRIORITIES AND STAFFING PERCENTAGES
Business Analysis: David Logie 50% (through 11/30)
Development:: Bill West 50%
Testing: Hari 25%
Priority | Item # | Description | BA Level of Effort | BA - % Complete | DEV Level of Effort | DEV - % Complete | TEST Level of Effort | TEST - % Complete | Process Owner | Scheduled Release |
---|---|---|---|---|---|---|---|---|---|---|
1 | R-X | CMDB Release 5 and 6 | ? | ? | ? | ? | ? | ? | ? | ? |
START REPLACEMENT PRIORITIES AND STAFFING PERCENTAGES
Business Analysis: Kesha Patel 50%
Development:: David Backeberg 100%, Fruition Consultants
Testing: Hari Adusumilli 50%
Priority | Item # | Description | BA Level of Effort | BA - % Complete | DEV Level of Effort | DEV - % Complete | TEST Level of Effort | TEST - % Complete | Scheduled Release |
---|---|---|---|---|---|---|---|---|---|
1 | R-X | START Replacement Forms/Workflow | Months | 98% | Months | 90% | Months | 90% | 11/22/2013 |
OUTSTANDING ACTION ITEMS
- Process Owners to review their list of enhancements in their area and see what they can remove so that we can reduce the amount of work in the bucket (aka the demand) (from 8/19)
- Chloe to add an agenda item to one of our upcoming meetings to discuss the enhancement/defect logging process and how an item makes it from request to release (from 7/22)
- Will add this to an upcoming meeting
- Tim to come up with a plan to retire the affected components that are in the CI field (from 7/29)