Work Priority/Sequence
See: Process Owners - Operational
Release Status
http://trello.com/b/jwlT2lWa/servicenow
Roll Call
Name | Org | Present |
---|---|---|
Soren Sonsen | Yale Director | |
David Backeberg | Yale Dev | |
Chloe Turnbull | Yale BA | |
Hari Adusumilli | Yale QA | |
Tim Nichols | Yale | |
Christine Costantino | Yale | |
Ricardo Chavira | Yale | |
Adriene Radcliffe | Yale | |
Dave Rich | Yale | |
Rosann Adams | Yale | |
Fred Roos | FP |
Agenda
Please come to the meeting on time & prepared
- If you don't have a status change, that's OK! Just say so.
- What did you do yesterday?
- What are you doing next? (like, within the next day or two? Break "ongoing" tasks into pieces).
- What obstacles are slowing/stopping progress?
Discussion
Soren Sonsen:
- Walking through defect list
- Reminded us that there's a lot of stuff that seems to be good candidates for release when Chloe gets back
David Backeberg:
- Done:
- Closed out several group / user changes from RTS queue, including big one from Casey Watts
- Heard from Laurie Seluga that there's another person besides Casey interested in SN stuff
- Got a confirmation that billing is working okay with microtiers, relayed that to Deb Bettley
- CMDB, confirmed that several machines are undiscoverable
- D916 seemingly fixed
- Next:
- D645, do that first
- D916; still need to test ONE PTAEO and NO PTAEO cases
- Meeting with Fred in the coming days; already requested a meeting with him.
- Obstacles:
- Backlog:
Tim:
- Done:
- Meeting up with David Logie after this meeting
- Integration problem with Quickbase; need a new account
- Next:
- Continuing to emphasize importance of CMDB stuff.
- Backlog:
Hari:
- Done:
- Progress on defects, the pile is shrinking.
- Next:
- R1041, need more test cases, clarification from some expert on Change module.
- R1109 hpc service
- Obstacles:
- Backlog:
Chloe:
- Done:
- on vacation
- Next:
- UAT coming up for FASIT stuff, R1139 plus others. 1138, 1140, 1141. On Wednesday.
- Going to associate provider services with user groups
- Need to meet up with Dave regarding workflow, FASIT requirement
- Backlog:
Ricardo:
- Done:
- Things look good with provider services and associations
- Next:
- Obstacles:
- Backlog:
Adriene:
- Done:
- ordered coffee
- Next:
- Obstacles:
- Backlog:
Christine:
- Done:
- Next:
- lots of meetings today
- Obstacles:
- Backlog:
Dave Rich:
- Done:
- Regression test suite in ALM
Obstacles:
- Backlog:
Michael Hale:
- Next:
- Obstacles:
Jim McKay:
Allen:
- Done:
- Next:
John:
- Done:
- Next:
Rosann Adams:
questions for us, hoping to meet one-on-one:
- What is the team doing well?
- If we could do one thing better, what would it be?
- What do we need to stop doing, that's not making things better?
- ORG chart as distributed by Adriene in email is probably not the ORG going forward
- Likely that team members will move around physically in the building. Jane's team is on the 5th floor. Space team will figure it out in the future. Not currently any space to move ITSM upstairs. Possibly as soon as two months.