General Info

Regularly scheduled weekly status for START replacement

Call-In Info

  1. Dial 6-5777, (203) 436-5777 or (855) 925-3266.
  2. Enter Meeting ID 60612 and #.
  3. Speak your name, then enter #.

Roll Call

Name

Org

Present

Christine Costantino

Yale

(tick)

Kesha Patel

Yale

(error)

Barbara Manville

Yale

(tick)

David Backeberg

Yale

(tick)

Hari Adusumilli

Yale

(tick)

Wendy Battles

Yale

(tick)

Bob Liu

Yale

(tick)

Jeff Euben

Yale

(error)

Roger Kennedy

Yale

(tick)

Jay Johnson

Yale

(tick)

Adriene Radcliffe

Yale

(tick) (optional)

Jane Livingston

Yale

(error) (optional)

Agenda

Please come to the meeting on time & prepared

  1. Review Project Plan deliverables
  2. Obstacles & Risks
  3. Issues or risks to discuss with the ITSM program committee?

Discussion

* Roger led the discussion, Christine took notes.

Review of Project Plan

Plan Phase

  • Project Plan (Christine) - 75%. Need to add a few more tasks, clean-up dates and dependencies
  • Risk Log (Christine) - 50%. Update with resource risks
  • Stakeholder Impact Analysis (Wendy) - 100% complete & signed-off
  • Communication Plan (Wendy) - 100% complete & signed-off

Analyze Phase (As-Is)

  • Display responsibilities - Oracle access (move to IAM?) Client Accts uses this
  • Referential Data (Barb) - As-is = 100% To-be - request to enter into START?
  • Invoice approval - R12 project is taking care of this.

Design Phase (To-be)

  • Business Requirements Doc (Kesha)

- Wendy and Janet - financial notification - 4/26

- Telephone sets and lines - 25%

- People lists - request Barb - 16 people lists used in various places, 1 day per list, 1 day per req - 32 days work (PL SQL)

- Wendy - training plan and support plan

- Wendy focus groups scheduling - mon due 4/22

- PTAEO validator - 2 more reqs multiple ptaeos, copy pataeos

- financial approval - 4/24 from Fruition

- ref table - meeting today 

- telephone sets & lines - 

- SciQuest - fullfilment - Rob Bores, Kahzi? IAM provisioning!

- Pagers - 75% pending financial workflow

- Ethernet - dependency ref table 

- Pagers - 80% 

Obstacles - fulfillment work? SOWs for web methods - Igor to analyze and give to Jeff's team. mid-May (after May 13) 

Risks

  • Resources - We are in the process of hiring another BA to work on START 50%. Roger will talk to Michael Blomberg about a replacement for Barbara who is now down to 10% for April and May, 0% for June.

Obstacles

  • Janet Jeddry is out this week. Wendy and Janet will finish up the notifications next week.
  • Kesha will be focusing on the CMDB project this week and will not be able to work on START until next week.

Issues/Concerns

  •  

Action Items

Christine

  • Update Work Plan and Risk Log

Wendy

  • Finish financial approval notifications with Janet
  • Start Training plan

Kesha

  • Start working on the Business Requirements Doc

Barbara

  • People List request

Dave

  • Financial Approval workflow

Jay

  • Follow-up re: SciQuest provisioning

Hari

  • Start Test Plan document

Adriene

  • XTRAIN meeting next week