General Info
Regularly scheduled weekly status for START replacement
Call-In Info
- Dial 6-5777, (203) 436-5777 or (855) 925-3266.
- Enter Meeting ID 60612 and #.
- Speak your name, then enter #.
Roll Call
Name |
Org |
Present |
---|---|---|
Christine Costantino |
Yale |
|
Kesha Patel |
Yale |
|
Barbara Manville |
Yale |
|
David Backeberg |
Yale |
|
Hari Adusumilli |
Yale |
|
Wendy Battles |
Yale |
|
Bob Liu |
Yale |
|
Jeff Euben |
Yale |
|
Roger Kennedy |
Yale |
|
Jay Johnson |
Yale |
|
Adriene Radcliffe |
Yale |
(optional) |
Jane Livingston |
Yale |
(optional) |
Agenda
Please come to the meeting on time & prepared
- Review Project Plan deliverables
- Obstacles & Risks
- Issues or risks to discuss with the ITSM program committee?
Discussion
* Roger led the discussion, Christine took notes.
Review of Project Plan
Plan Phase
- Project Plan (Christine) - 75%. Need to add a few more tasks, clean-up dates and dependencies
- Risk Log (Christine) - 50%. Update with resource risks
- Stakeholder Impact Analysis (Wendy) - 100% complete & signed-off
- Communication Plan (Wendy) - 100% complete & signed-off
Analyze Phase (As-Is)
- Display responsibilities - Oracle access (move to IAM?) Client Accts uses this
- Referential Data (Barb) - As-is = 100% To-be - request to enter into START?
- Invoice approval - R12 project is taking care of this.
Design Phase (To-be)
- Business Requirements Doc (Kesha)
- Wendy and Janet - financial notification - 4/26
- Telephone sets and lines - 25%
- People lists - request Barb - 16 people lists used in various places, 1 day per list, 1 day per req - 32 days work (PL SQL)
- Wendy - training plan and support plan
- Wendy focus groups scheduling - mon due 4/22
- PTAEO validator - 2 more reqs multiple ptaeos, copy pataeos
- financial approval - 4/24 from Fruition
- ref table - meeting today
- telephone sets & lines -
- SciQuest - fullfilment - Rob Bores, Kahzi? IAM provisioning!
- Pagers - 75% pending financial workflow
- Ethernet - dependency ref table
- Pagers - 80%
Obstacles - fulfillment work? SOWs for web methods - Igor to analyze and give to Jeff's team. mid-May (after May 13)
Risks
- Resources - We are in the process of hiring another BA to work on START 50%. Roger will talk to Michael Blomberg about a replacement for Barbara who is now down to 10% for April and May, 0% for June.
Obstacles
- Janet Jeddry is out this week. Wendy and Janet will finish up the notifications next week.
- Kesha will be focusing on the CMDB project this week and will not be able to work on START until next week.
Issues/Concerns
Action Items
Christine
- Update Work Plan and Risk Log
Wendy
- Finish financial approval notifications with Janet
- Start Training plan
Kesha
- Start working on the Business Requirements Doc
Barbara
- People List request
Dave
- Financial Approval workflow
Jay
- Follow-up re: SciQuest provisioning
Hari
- Start Test Plan document
Adriene
- XTRAIN meeting next week