Skip to end of metadata
Go to start of metadata

You are viewing an old version of this page. View the current version.

Compare with Current View Page History

« Previous Version 6 Next »

General Info

Scheduled for every other week to discuss the START replacement project

Call-In Info

  1. Dial 6-5777, (203) 436-5777 or (855) 925-3266. 
  2. Enter Meeting ID: 60612 and #.
  3. Speak your name, then enter #.

Roll Call

Name

Org

Present

Christine Costantino

Project Manager, START Replacement Project

(tick)

Roger Kennedy

Portfolio Manager, Office of the CIO

(tick)

Adriene Radcliffe

Director, Service Management & e-Services

(tick)

Karen Polheums (stand-in for Adriene)

Sponsor, ITS

(tick)

Ronn Kolbash

AVP, Yale Shared Services

(tick)

Liz Burnell

Director, IAM

(tick)

Jackie Tucker

Sr. Director, Business Solutions

(tick)

Julie Grant

AVP, Business Operations

(error)

Nancy Scanlon

Operations Manager, Business Operations

(error)

Agenda

Please come to the meeting on time & prepared

  1. Update from IAM
  2. Project Updates
  3. Project Milestones
  4. Project Financials
  5. Risks / Issues

Slide Deck

Discussion

Project Updates

Project Milestones

  • 6/14 - ESS updates
  • 6/30 - Telecom, Ethernet, Back-up, Email requests
  • 7/15 - Access requests
  • 8/31 - Training begins
  • 9/27 - Deployment
  • IAM
    o Enterprise Directory delivery in December,2013
    o E-mail, Netid, PINS delivery March 2014
    o Training scheduling should be approved by Julie Grant
  • START Analysis
    o START requests that go through XTRAIN is still being analyzed
    o Business Manager lists still being analyzed
    o People lists that are not used such as Expert lists will not be replaced
    o Review of people lists usability being analyzed such as DSP lists
    o Nancy will mock up a user request form for People list requests
  • START Testing in a patched environment
    o Oracle upgrade Sept. 21
    o Results August 2
  • START Replacement project rollout
    o Sept 30 – ITS services such as pagers, telephones etc...
    o Xtrain is TBD
    o IAM will e responsible for User Access requests
  • Jackie Tucker has requested an IAM roadmap of deliverables
  • Move 8/1 ROC meeting until testing and
  • analysis is complete

Risks / Issues

Concerns

Past Meetings