Lemon Pig Mid Sprint Review

Lemon Pig Mid Sprint Review

Jan 10, 2024

Wins

  1. YSB - On track to complete initial dev work before 1/10 due date

  2. FAS - Version 1 on track to be completed

Concerns

  1. New high priority work - Initial planning is no longer relevant - new projects and deadlines have shifted.

  2. Burndown Chart does not capture all work - New AI project and SPEC work is not reflected in the burndown chart.

  3. QA strategy - Need to develop strategy for QA on FRMS and SDF - deadlines of January may be impacted.

  4. FRMS PTO - Jacky is out of office until 1/24 and will not be able to provide feedback or approval on work until then, which may impact deliver date.

Focus

  1. Update goals if needed

  2. Remove work where possible to help re-prioritize

  3. Determine QA strategy for FRMS and SDF

 

Goal

Progress

Notes

 

Goal

Progress

Notes

1

Ops Dash - Dev work compete by 1/10

On Track

  • Initial commitment of work on track to be completed before end of day

  • Additional work and changes added, may not be reflected in metrics

2

Ops Dash - Complete and prioritize any accessibility tickets identified

Complete

  • Initial commitment complete

  • Further changes may result in additional accessibility tasks

3

Ops Dash - Create Mockups of UI/UX Feedback

Complete

 

4

Ops Dash - Begin performance and regression testing

Dependent, On Track

  • Blocked by goal 1

5

Ops Dash - Begin research for Buildings and Services

 

 

6

CEA - Complete Phase 1

Blocked

Need Credit Card information to complete

7

SDF - Duplicate database in Outsystems

On Track

 

8

SDF - CAS Authentication

Complete

 

9

FMP - Server Update

Complete

 

10

Maintenance - GitLab Patching

Complete

 

Burndown Chart - Time Remaining -

Screen Shot 2024-01-10 at 10.39.01 AM.png