Lemon Pig Mid Sprint Review
Jan 10, 2024
Wins
YSB - On track to complete initial dev work before 1/10 due date
FAS - Version 1 on track to be completed
Concerns
New high priority work - Initial planning is no longer relevant - new projects and deadlines have shifted.
Burndown Chart does not capture all work - New AI project and SPEC work is not reflected in the burndown chart.
QA strategy - Need to develop strategy for QA on FRMS and SDF - deadlines of January may be impacted.
FRMS PTO - Jacky is out of office until 1/24 and will not be able to provide feedback or approval on work until then, which may impact deliver date.
Focus
Update goals if needed
Remove work where possible to help re-prioritize
Determine QA strategy for FRMS and SDF
| Goal | Progress | Notes |
---|---|---|---|
1 | Ops Dash - Dev work compete by 1/10 | On Track |
|
2 | Ops Dash - Complete and prioritize any accessibility tickets identified | Complete |
|
3 | Ops Dash - Create Mockups of UI/UX Feedback | Complete |
|
4 | Ops Dash - Begin performance and regression testing | Dependent, On Track |
|
5 | Ops Dash - Begin research for Buildings and Services |
|
|
6 | CEA - Complete Phase 1 | Blocked | Need Credit Card information to complete |
7 | SDF - Duplicate database in Outsystems | On Track |
|
8 | SDF - CAS Authentication | Complete |
|
9 | FMP - Server Update | Complete |
|
10 | Maintenance - GitLab Patching | Complete |
|
Burndown Chart - Time Remaining -