Analyze Phase (As-Is)
- Display responsibilities - Oracle access (move to IAM?) Client Accts uses this
- Referential Data (Barb) - As-is = 100% To-be - request to enter into START?
- Invoice approval - R12 project is taking care of this(Christine) - 50% Sent email to IAM folks to find out if this should be part of Sailpoint.
Design Phase (To-be)
- Business Requirements Doc (Kesha)
...
- Financial notification (Wendy and Janet - financial notification - 4/26
...
- Telephone sets and lines - 25%
...
- People lists - request Barb - 16 people lists used in various places, 1 day per list, 1 day per req - 32 days work (PL SQL)
...
- Wendy - training plan and support plan
...
- Wendy focus groups scheduling - mon due 4/22
Build Phase -
- PTAEO validator - 2 more reqs multiple ptaeos, copy pataeos
...
- financial approval - 4/24 from Fruition
...
- ref table - meeting today
...
- telephone sets & lines -
...
- SciQuest - fullfilment - Rob Bores, Kahzi? IAM provisioning!
...
- Pagers - 75% pending financial workflow
...
- Ethernet - dependency ref table
...
- Pagers - 80%
Obstacles -
- fulfillment work? SOWs for web methods - Igor to analyze and give to Jeff's team. mid-May (after May 13)
Risks
- Resources - We are in the process of hiring another BA to work on START 50%. Roger will talk to Michael Blomberg about a replacement for Barbara who is now down to 10% for April and May, 0% for June.
...
- Janet Jeddry is out this week. Wendy and Janet will finish up the notifications next week.
- Kesha will be focusing on the CMDB project this week and will not be able to work on START until next week.
Issues/Concerns
...
Action Items
Christine
- Update Work Plan and Risk Log
...