No meeting held - project summary provided below
Project Summary
Project Updates
- Focus Groups have been scheduled for 5/28, 5/29, 6/3 and 6/4.
- Christine and Wendy presented the project overview to the IT Partners group on 5/16.
UI Discussion (5/
Financial Update
Review milestones for delivery
- Plan/Analyze - 3/28 (99% complete)
- Design/Build/Test - 12/1 - 8/1
- ESS changes - 5/15
- Currently in Design and Build phases for Telecom (Mobile device, Pagers, Telephone sets & lines), Ethernet, and Central Campus Backup requests.
- Training - 8/1 - 9/30
- Deploy & Warranty - 9/1 - 9/30
Issues/Concerns -
Past Meetings