Wins

  1. FAS v1.1 Released and hand off complete!

  2. Successful SDF demo with client

  3. SSL Cert completion on track

Concerns

  1. Outside Project work blockers - Meaningful planning is very difficult without full picture of work being done by team. Difficult to get answers and input on CAD projects from team members focused on outside work.

  2. Burndown Chart does not capture all work - New AI project and SPEC work is not reflected in the burndown chart. Very difficult to plan.

  3. QA strategy - Need to develop strategy for QA on FRMS and SDF - team is confused and may impact ability to deliver QA’d product to client in timely manner.

Focus

  1. YSB back in focus as outside projects wind down

  2. Formalizing SDF work and planning ahead, updating project plan

  3. Update team roadmap - Outstanding Proposals (CEA, Reservations), allocating resources as projects wind down

Goal

Progress

Notes

1

YSB - Complete Everbridge Research

In Progress

  • Team split between SPEC and YSB

2

FRMS - Complete 5 reports

Blocked

  • PDF plugin causing technical issues. Chris has escalated the issue to Doug.

3

YIM - Complete Annual Database Configuration

In Progress

  • Ed has been focused on SDF, but plans on finishing before end of sprint

4

YSoA - Complete Annual Database Configuration

In Progress

  • Ed has been focused on SDF, but plans on finishing before end of sprint

5

SDF - Complete Commitments Screen

v1 Complete

  • Initial build complete. Grecia will be assisting with tweaking the front end build.

6

SDF - Disbursement Creation Routine

Blocked

  • Through conversations with client, more work was needed on baseline architecture before this could be completed.

7

SDF - Define testing strategy

Blocked

  • Rosa needs input from Netal to proceed.

8

Maintenance - SSL Cert Review

In Progress

  • Dev complete, Test in progress. On track.

Burndown Chart - Time Remaining -

Screen Shot 2024-02-07 at 1.06.31 PM.png

Sprint Health

Screen Shot 2024-02-07 at 1.06.11 PM.png