Table of Contents |
---|
General Info
Scheduled for every 3 weeks other week to discuss the START replacement project.
Call-In Info:
- Dial 6-5777, (203) 436-5777 or (855) 925-3266.
- Enter Meeting ID: 60612 and #.
- Speak your name, then enter #.
Roll Call
Name | Org | Present | |
---|---|---|---|
Christine Costantino | PM, ITSM Project Manager, START Replacement Project |
| |
Roger Kennedy | Portfolio Manager, Office of the CIO |
| |
Wendy Battles | CM, ITS Adriene Radcliffe | Sponsor / Director, Service Management & e-Services |
|
Karen Polheums (Polhemus | Sponsor stand-in for Adriene ) Sponsor, ITS |
| |
Ronn Kolbash | Sponsor / AVP, SSC Yale Shared Services |
| |
Liz Burnell | Director, IAM |
| |
Jackie Tucker | Sr. Director, Business Solutions |
| |
Julie Grant | AVP, Business Operations |
| |
Nancy Scanlon | Operations Manager, Business Operations |
|
Agenda
Please come to the meeting on time & prepared
- Update from IAMIntroductions
- Project Updates
- Project MilestonesProject Financials
- Risks / Issues
- Discussion
- Next Steps
Slide Deck
Discussion
Introductions
- Karen is transitioning out of the project now that Adriene is back from medical leave.
Project Updates
Project Milestones
- 6/14 - ESS updates
- 6/30 - Telecom, Ethernet, Back-up, Email requests
- 7/15 - Access requests
- 8/31 - Training begins
- 9/27 - Deployment
Project Financials
FY13 (final)
Approved Funding | $100,000.00 |
Resource Costs | $208,307.88 |
Training Costs | $1,395.00 |
Total Costs (to date) | $209,702.88 |
Variance (to date) | $109,702.88 |
EAC | $258,749.88 |
ETC | $49,047.00 |
VAC | -$158,749.88 |
FY14
Approved Funding | $100,000.00 |
Resource Costs | $208,307.88 |
Training Costs | $1,395.00 |
Total Costs (to date) | $209,702.88 |
Variance (to date) | $109,702.88 |
EAC | $258,749.88 |
ETC | $49,047.00 |
VAC | -$158,749.88 |
Risks / Issues
...
- Telecom & IT Requests (Pagers, Telephone services, Mobile devices, Ethernet connection, Central campus backup)
- Email & NetID PINs (YaleConnect, Email alias, NetID PINs)
- Impact for Client Accts - Sept. release would require manual work (Avg. 450 requests/month) - Unacceptable.
- Automation will become available with IAM solution (Release 1 ~FY14 Q3).
- Access Requests & Training (Analysis & Design) Oracle – move training to TMS, decommission XTRAIN, SciQuest, Xpress Shipping. Some manual work today will be included in new request process. Process Owners to review training requirements
- People Lists (Analysis & Design phase) - Originally part of IAM project portfolio, solution not ready. Building with Oracle until IAM solution is ready.
- START Replacement Training - Just-in-time, to coincide with release(s). To take place 4 weeks prior for big bang release
Project Milestones
- Sept. - Telecom & IT requests built
- Sept 30 - Original START release date
- Oct. - Access requests (XTRAIN) & People Lists built?
- 4 weeks before release - Training
- ~FY14 Q3 (TBD) - IAM Release 1 & START Release for YaleConnect, Email alias, NetID PINs, full START service catalog?
Risks / Issues
- New process for Access requests & Training will not be ready for Sept.
- New process for People Lists will not be ready for Sept.
- Email & NetID PIN Automation will not be ready for Sept.
- Oracle Upgrade planned for Sept 21. We are currently testing START against patch (in a patched environment) and will be completed Aug. 2.
Discussion
- Modify deployment approach: phased releases vs. big bang release?
- Sept – ITS services: pagers, telephone services, mobile devices, central campus backup, ethernet
- If phased approach, there may be opportunities to include other Access requests such as YBT, IRES.
- IAM
- Enterprise Directory delivery in December 2013
- NetAdmin functions related to YaleConnect, E-mail alias, Netid PINS delivery sometime around March 2014
Next Steps / Action Items
- Meeting with IAM re: Access provisioning - Liz
- IAM roadmap of deliverables - Liz
- Integrated view of START & IAM projects - Liz & Christine
- Move ROC presentation to 8/15 - Christine
- Presentation to the Operating Group will be postponed - Wendy
- Meeting with Process Owners to review access & training policies - Nancy
- Next Steering Committee meeting (8/7) - Present recommended path for releases - Christine
Past Meetings
Page Tree | ||
---|---|---|
|