Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.
Comment: Migrated to Confluence 4.0
Table of Contents

General Info

Scheduled for every 3 weeks other week to discuss the START replacement project.

Call-In Info:

  1. Dial 6-5777, (203) 436-5777 or (855) 925-3266. 
  2. Enter Meeting ID: 60612 and #.
  3. Speak your name, then enter #.

Roll Call

Name

Org

Present

Christine Costantino

PM, ITSM Project Manager, START Replacement Project

(tick)

Roger Kennedy

Portfolio Manager, Office of the CIO

(tick)

Wendy Battles

CM, ITS Adriene Radcliffe

Sponsor / Director, Service Management & e-Services

(tick)

Karen Polheums (Polhemus 

Sponsor stand-in for Adriene )

Sponsor, ITS

(tick)

Ronn Kolbash

Sponsor / AVP, SSC Yale Shared Services

(tick)

Liz Burnell

Director, IAM

(tick)

Jackie Tucker

Sr. Director, Business Solutions

(tick)

Julie Grant

AVP, Business Operations

(error)

Nancy Scanlon

Operations Manager, Business Operations

(tick)

Agenda

Please come to the meeting on time & prepared

  1. Introductions
  2. Project Updates
  3. Project Milestones
  4. Project Financials
  5. Risks / Issues
  6. Discussion
  7. Next Steps

Slide Deck

START_update_11June201326July2013.pptx

Discussion

Introductions

  • Karen is transitioning out of the project now that Adriene is back from medical leave.

Project Updates

  • Communications – 4 Focus Groups complete, 1 added for 6/18
  • ITS Website UI – easier to manipulate with CSS, mobile-friendly
  • FY14 Carryover ($137K) – Recalculating remaining work effort to update resource plan and funding needed. ROC review TBD.
  • ESS update releases 6/14 & 6/21 (new incident form)
  • Telecom, Ethernet, Financial Approval, PTAEO = 90% complete
  • Backup, Email, People Lists, Access requests (XTRAIN) = Design in progress

Project Milestones

  • 6/14 - ESS updates
  • 6/30 - Telecom, Ethernet, Back-up, Email requests
  • 7/15 - Access requests
  • 8/31 - Training begins
  • 9/27 - Deployment

Project Financials

Approved Funding

$100,000.00

Resource Costs

$208,307.88

Training Costs

$1,395.00

Total Costs (to date)

$209,702.88

Variance (to date)

$109,702.88

EAC

$258,749.88

ETC

$49,047.00

VAC

-$158,749.88

Risks/Issues

  • XTRAIN – Need resources to analyze each training class individually, create Solution Design processes.
  • People Lists – Need resources to create Solution Design for API needed to connect ServiceNow to Oracle. Originally part of IAM project portfolio.

Concerns

  • Ronn wants to know what the schedule is for IAM's Sailpoint releases as it related to NetAdmin and Client Accounts.Telecom & IT Requests (Pagers, Telephone services, Mobile devices, Ethernet connection, Central campus backup) 
  • Email & NetID PINs (YaleConnect, Email alias, NetID PINs)
    • Impact for Client Accts - Sept. release would require manual work (Avg. 450 requests/month) - Unacceptable.
    • Automation will become available with IAM solution (Release 1 ~FY14 Q3).
  • Access Requests & Training (Analysis & Design) Oracle – move training to TMS, decommission XTRAIN, SciQuest, Xpress Shipping. Some manual work today will be included in new request process. Process Owners to review training requirements
  • People Lists (Analysis & Design phase) - Originally part of IAM project portfolio, solution not ready. Building with Oracle until IAM solution is ready.
  • START Replacement Training - Just-in-time, to coincide with release(s). To take place 4 weeks prior for big bang release

Project Milestones

  • Sept. - Telecom & IT requests built
  • Sept 30 - Original START release date
  • Oct. - Access requests (XTRAIN) & People Lists built?
  • 4 weeks before release - Training
  • ~FY14 Q3 (TBD) - IAM Release 1 & START Release for YaleConnect, Email alias, NetID PINs, full START service catalog?

Risks / Issues

  • New process for Access requests & Training will not be ready for Sept.
  • New process for People Lists will not be ready for Sept.
  • Email & NetID PIN Automation will not be ready for Sept.
  • Oracle Upgrade planned for Sept 21. We are currently testing START against patch (in a patched environment) and will be completed Aug. 2.

Discussion

  • Modify deployment approach: phased releases vs. big bang release?
    • Sept – ITS services: pagers, telephone services, mobile devices, central campus backup, ethernet
    • If phased approach, there may be opportunities to include other Access requests such as YBT, IRES.
  • IAM
    • Enterprise Directory delivery in December 2013
    • NetAdmin functions related to YaleConnect, E-mail alias, Netid PINS delivery sometime around March 2014

Next Steps / Action Items

  • Meeting with IAM re: Access provisioning - Liz
  • IAM roadmap of deliverables - Liz
  • Integrated view of START & IAM projects - Liz & Christine
  • Move ROC presentation to 8/15 - Christine
  • Presentation to the Operating Group will be postponed - Wendy
  • Meeting with Process Owners to review access & training policies - Nancy
  • Next Steering Committee meeting (8/7) - Present recommended path for releases - Christine

Past Meetings

Page Tree
root

...

START Steering Committee