Table of Contents

General Info

Regularly scheduled weekly status for START replacement.

Please let Christine know if you plan to call in.

Call-In Info

  1. Dial 6-5777, (203) 436-5777 or (855) 925-3266.
  2. Enter Meeting ID 60612 and #.
  3. Speak your name, then enter #.

Roll Call

Name

Org

Present

Christine Costantino

Yale

(tick)

Kesha Patel

Yale

(error)

Barbara Manville

Yale

(tick)

David Backeberg

Yale

(tick)

Hari Adusumilli

Yale

(tick)

Wendy Battles

Yale

(tick)

Bob Liu

Yale

(tick)

Jeff Euben

Yale

(error)

Roger Kennedy

Yale

(tick)

Jay Johnson

Yale

(tick)

Adriene Radcliffe

Yale

(tick) (optional)

Jane Livingston

Yale

(error) (optional)

Agenda

Please come to the meeting on time & prepared

  1. Review Project Plan deliverables
  2. Obstacles & Risks
  3. Issues or risks to discuss with the ITSM program committee?

Discussion

* Roger led the discussion, Christine took notes.

...

  • Project Plan (Christine) - 75%85%. Need to add a few more tasks, clean-up dates and dependencies
  • Risk Log (Christine) - 50%. Update with resource risks
  • Stakeholder Impact Analysis (Wendy) - 100% complete & signed-off
  • Communication Plan (Wendy) - 100% complete & signed-off

...

  • Display responsibilities (Christine) - 50% Sent email to IAM folks to find out if this should be part of Sailpoint (IAM tool).

Design Phase (To-be)

  • Business Requirements Doc (Kesha)
  • Financial notification (Wendy and Janet - financial notification - ) will complete for 4/26
  • Telephone sets and lines (Kesha) - 25%
  • People lists - request (Barb) - 16 people lists used in various places, will take approx. 1 day per list , and 1 day per req - = 32 days work (PL SQL).
  • Wendy - training plan and support plan
  • Wendy focus groups scheduling - mon Focus groups (Wendy) scheduling for early May, due 4/22

Build Phase

  • PTAEO validator (David) - 2 more reqs: multiple ptaeos, copy pataeosptaeos
  • financial Financial approval (David) - due 4/24 from Fruition
  • ref Ref table for Ethernet (David) - meeting today telephone sets & lines - 
  • SciQuest - fullfilment API (David) - Rob Bores (service owner), Kahzi (developer?) Requires IAM provisioning!
  • Pagers (David) - 75%, pending financial approval workflow
  • Ethernet - dependency ref table 
  • Pagers - 80% 

Obstacles

...

Test Phase

  • Pagers (Hari) - 80%, pending financial approval workflow

Risks

  • Resources - We are in the process of hiring another BA to work on START 50%. Roger will talk to Michael Blomberg about a replacement for Barbara who is now down to for the Poeple lists request; she is only 10% for April and May, 0% for June.

...

  • Janet Jeddry is out this week. Wendy and Janet will finish up the notifications next week.
  • Kesha will be focusing on the CMDB project this week and will not be able to work on START until next week.
  • Fulfillment work - SOWs for web methods - ask Igor to analyze, give to Jeff's team after May 13 (R12 release).

Issues/Concerns

  • IAM dependencies - Don Murphy and John Guidone will join us next week to talk about their project schedules/milestones.

Action Items

Christine

  • Update Work Plan and Risk Log
  • XTRAIN meeting

Wendy

  • Finish financial approval notifications with Janet
  • Start Training planSchedule focus groups

Kesha

  • Start working on the Business Requirements Doc

...

  • Financial Approval workflow

Bob

  • Update wireframes, screenshots of prototype

Jay

  • Follow-up re: SciQuest provisioning

...

Adriene

  • XTRAIN meeting next week

Release Status (START items labeled purple)

Wiki Markup
{iframe:src=https://trello.com/b/jwlT2lWa|width=1200|height=700}
text to show when browser does not support iframes
{iframe}