- Modify deployment approach: phased releases vs. big bang release?
- Sept 30 – ITS services: pagers, telephone services, mobile devices, central campus backup, ethernet
- If phased approach, there may be opportunities to include other Access requests such as pagersYBT, telephones etcIRES...
- IAM
- Enterprise Directory delivery in December 2013
- NetAdmin functions related to YaleConnect, E-mail alias, Netid PINS delivery sometime around March 2014
...
- Meeting with IAM re: Access provisioning - Liz
- IAM roadmap of deliverables - Liz
- Integrated view of START & IAM projects - Liz & Christine
- Move ROC presentation to 8/15 - Christine
- Presentation to the Operating Group will be postponed - WendyNancy will mock up a user request form for People list
- requestsMeeting with Process Owners to review access & training policies - Nancy
- Next Steering Committee meeting (8/7) - Present recommended path for releases - Christine