  • Modify deployment approach: phased releases vs. big bang release?
    • Sept 30 – ITS services: pagers, telephone services, mobile devices, central campus backup, ethernet
    • If phased approach, there may be opportunities to include other Access requests such as pagersYBT, telephones etcIRES...
  • IAM
    • Enterprise Directory delivery in December 2013
    • NetAdmin functions related to YaleConnect, E-mail alias, Netid PINS delivery sometime around March 2014

...

  • Meeting with IAM re: Access provisioning - Liz
  • IAM roadmap of deliverables - Liz
  • Integrated view of START & IAM projects - Liz & Christine
  • Move ROC presentation to 8/15 - Christine
  • Presentation to the Operating Group will be postponed - WendyNancy will mock up a user request form for People list
  • requestsMeeting with Process Owners to review access & training policies - Nancy
  • Next Steering Committee meeting (8/7) - Present recommended path for releases - Christine