Table of Contents |
---|
General Info
Regularly scheduled weekly status for START replacement.
...
- Dial 6-5777, (203) 436-5777 or (855) 925-3266.
- Enter Meeting ID 60612 and #.
- Speak your name, then enter #.
Roll Call
Name | Role | Present |
---|---|---|
Christine Costantino | PM |
|
Kesha Patel | BA |
|
Barbara Manville | SME / BA |
|
David Logie | BA |
|
David Backeberg | Tech Lead |
|
Hari Adusumilli | Test Lead |
|
Wendy Battles | CM |
|
Bob Liu | ITS Web Dev |
|
Roger Kennedy | Portfolio Manager |
|
Jay Johnson | IAM CM |
|
Jeff Euben | CTS Voice | (optional) |
Adriene Radcliffe | Sponsor | (optional) |
Jane Livingston | Sponsor | (optional) |
Agenda
Please come to the meeting on time & prepared
- Introduction of David Logie
- Review Action Items from last week
- Review Project Plan deliverables
- Obstacles & Risks
Discussion
* Roger led the discussion, Christine took notes.
...
- Christine - Update Work Plan and Risk Log , - Reschedule XTRAIN meeting (add include Roger) (, schedule meeting with Client Accounts )and David Logie
- Wendy - Finish financial approval notifications with Janet (Friday 5/3 w/Janet), Schedule focus groups all but one, need room (May 13, central side), need to set-up TMS and send communication
- Dave - Financial Approval workflow - UAT + defects, ESS work in queue - done
- Kesha - Telephone Services
- Barbara - People List requests
Review of Project Plan Deliverables
...
- Financial notification (Wendy) - 5/3
- Telephone sets and lines (Kesha) - 100%
- People lists request (Barb) - 16 people lists used in various places, will take approx. 1 day per list and 1 day per req = 32 days work (PL SQL).Travel Arranger req document - meeting with Travel folks
- Focus groups (Wendy) - all but one finished - change to 5/24
- Generate NetID PIN - David LogeTravel Arranger - Barbara - req document - today? meeting with Travel
Build Phase
- ESS requirements for 5/15,
- PTAEO validator (David) - 2 more reqs: multiple ptaeos, copy ptaeos - PTAEO sprinkles
- Financial approval (David) - Frution is working on defects
- Ref table for Ethernet (David) - 75% passed QA, advance to prod - to be released
- SciQuest API (David) - Rob Bores (service owner), Kahzi (developer?) Requires IAM provisioning
- Pagers (David) - 100%
- Mockup for Telephone sets & lines - 5% due 5/3
- Mobile Device - updatesfix dates
- Fix CCB date
- Ethernet - Fruition 5/10
- Order Guides - fix dates
- Web - Incidents 100%, May Cart 100%
...
Release Status (START items labeled purple)
...
Wiki Markup |
---|
{iframe:src=https://trello.com/b/jwlT2lWa |
...
|width |
...
=1200 |
...
|height |
...
=700 |
...
} text to show when browser does not support iframes |
...
{iframe} |
Past Meetings
Page Tree | ||
---|---|---|
|