- If you don't have a status change, that's OK! Just say so.
- What did you do yesterday?
- What are you doing next? (like, within the next day or two? Break "ongoing" tasks into pieces).
- What obstacles are slowing/stopping progress?
Discussion
David:
- Done:
- pushed PRE-PROD last night
- worked with Fruition on R854 financial approval workflow attached to Pager delete
- working with Fruition on R924 PTAEO copy button; need to move it to test
- finished a bunch of requirement logging in HPQC
- Next:
- still need to log defects from UAT review for financial approvalMeeting with Kesha today for UAT on R847
- Need to resolve remaining conundrums regarding financial workflow defects
- need to meet with Chloe, Christine, Kesha after call, and after fruition check-in call
- Obstacles:
- Not releasing ESS; be careful with PROD push
- Backlog:
...
- Done:
- Next:
- working on a CMDB release, to be done ASAP
- look at R793 feedback
- re-push to test
- next dev doc/change request
- R798 - incident surveys
- Obstacles:
- Backlog:
- Request Process functional doc draft
- schedule a SN KB hackathon
Hari:
- Done: Obstacles:
R672/R836 ESS waiting until R923 done.
R488 fixing building data
R923 ESS requests closed
R723 went into release - Next:
Regression in PRE-PROD - regression in progress, nothing found so far
- Next:
- continuing in regression
- Obstacles:
- confusion on requirements regarding CMDB
- Backlog:
Bob:
- Done:
- Next:
- R70 mobile approval
- Obstacles:
- access on prod (I will get this for you when you're ready to migrate work to prod -bw)
- Backlog:
...
- Done:
- Next:
- Obstacles:
- Backlog:
Chloe:
- Done:
- R780 SDR follow-up (meeting w/ Marcus)
- R786 UAT follow-up (patterson, panko)
- R791 UAT follow-up (patterson, panko)
- work on user story template
- R792 UAT follow-up (Andre)sent release notes this morning
- Next:
- release tonight
- Obstacles:
- Backlog:
Kesha:
- Done:
- finished diagrams for Phone Services
- Add new phone service is already signed off
- Next:
- working on revision to phone service; yet more re-work
- working on visio for mobile device
- central campus backup (meeting moved to next week)
Tim:
*Done
- gave details on CMDB project at Friday meeting
- 29 requirements
- gave details on CMDB project at Friday meeting
- Next:
- still working on release one CMDB
Adriene:
- Done:
- Next:
- Obstacles:
- Backlog:
Christine:
- Done:
- Next:
- doing UAT on ESS requirements: 923,652,654,836,671setting up meeting with Jeff Capuano, Mark regarding ESS
- Obstacles:
- Backlog:
Jason:
- Done:
- Next:
- Obstacles:
- Backlog:
...