Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • Modify deployment approach: phased releases vs. big bang release?
    • Sept 30 – ITS services: pagers, telephone services, mobile devices, central campus backup, ethernet
    • If phased approach, there may be opportunities to include other Access requests such as pagers, telephones etc..YBT, IRES.
  • IAM
    • Enterprise Directory delivery in December 2013
    • NetAdmin functions related to YaleConnect, E-mail alias, Netid PINS delivery sometime around March 2014

...

  • Meeting with IAM re: Access provisioning - Liz
  • IAM roadmap of deliverables - Liz
  • Integrated view of START & IAM projects - Liz & Christine
  • Move ROC presentation to 8/15 - Christine
  • Nancy will mock up a user request form for People list requestsMeeting with Process Owners to review access & training policies - Nancy
  • Next Steering Committee meeting (8/7) - Present recommended path for releases - Christine
  • Get list of Access requests outsider of START - Christine

Past Meetings

{pagetree:root=START Steering Committee