Please come to the meeting on time & prepared

  1. Update from IAM
  2. Project Updates
  3. Project Milestones
  4. Project Financials
  5. Risks / Issues

Slide Deck

...

Discussion

Project Updates

...

Project Milestones

  • 6/14 - ESS updates
  • 6/30 - Telecom, Ethernet, Back-up, Email requests
  • 7/15 - Access requests
  • 8/31 - Training begins
  • 9/27 - Deployment

Project Financials

FY13 (final)

Approved Funding

$100,000.00

Resource Costs

$208,307.88

Training Costs

$1,395.00

Total Costs (to date)

$209,702.88

Variance (to date)

$109,702.88

EAC

$258,749.88

ETC

$49,047.00

VAC

-$158,749.88

Risks/Issues

  • XTRAIN – Need resources to analyze each training class individually, create Solution Design processes.
  • People Lists – Need resources to create Solution Design for API needed to connect ServiceNow to Oracle. Originally part of IAM project portfolio.

Concerns

...

FY14

Approved Funding

$100,000.00

Resource Costs

$208,307.88

Training Costs

$1,395.00

Total Costs (to date)

$209,702.88

Variance (to date)

$109,702.88

EAC

$258,749.88

ETC

$49,047.00

VAC

-$158,749.88

Risks / Issues

Concerns