* Roger led the discussion, Christine took notes.

Review of Project Plan

Plan PhaseDesign Phase

- Wendy and Janet - financial notification - 4/26

- Telephone sets and lines - 25%

- People lists - request Barb - 16 people lists used in various places, 1 day per list, 1 day per req - 32 days work (PL SQL)

- Wendy - training plan and support plan

- Wendy focus groups scheduling - mon due 4/22

- PTAEO validator - 2 more reqs multiple ptaeos, copy pataeos

- financial approval - 4/24 from Fruition

- ref table - meeting today 

- telephone sets & lines - 

- SciQuest - fullfilment - Rob Bores, Kahzi? IAM provisioning!

- Pagers - 75% pending financial workflow

- Ethernet - dependency ref table 

- Pagers - 80% 

Obstacles - fulfillment work? SOWs for web methods - Igor to analyze and give to Jeff's team. mid-May (after May 13) 

  • Project Plan (Christine) - in draft. Christine will schedule a project planning meeting for Friday 11-1pm - Kesha will be out; include Don, Jay, John, Matt
  • Risk Log (Christine) - in draft. update adding resource risk for Kathleen Reilly
  • Stakeholder Impact Analysis (Wendy) - complete, just need sign-off from Liz, Jane, & Jay
  • Communication Plan (Wendy) draft - need sign-off from Liz, Jane, Jay

...