- Telecom & IT Requests
- Training in October
- Planned deployment Nov 1.
- Release: Pagers, Telephone services, Ethernet connection, Mobile devices, ITS backup service (Central campus backup)
- Access Requests & Training, People Lists
- Policy review with Oracle Process Owners - Nancy
- User interface & API to Oracle, SciQuest, Xpress Shipping
- Training in November? Deploy in December? Decommission XTRAIN
- Email & NetID PINs (
- User interface for YaleConnect, Email alias, NetID PINs
- Impact for Client Accts - Sept. release would require manual work (Avg. 450 requests/month) - Unacceptable.
- Automation will become available with IAM solution (Release 1 ~FY14 Q3).
- –
- to
- People Lists (Analysis & Design phase) - Originally part of IAM project portfolio, solution not ready. Building with Oracle until IAM solution is ready.
- START Replacement Training - Just-in-time, to coincide with release(s). To take place 4 weeks prior for big bang release
- be completed in December
- IAM-ServiceNow API integration
- Deployment with IAM Release 1 (~March 2014)
Project Milestones
- Month of Oct. - Approver and fulfillment training
- Nov. 1 - Deploy ITS service requests for pagers, telephone services, mobile devices, Ethernet connection and ITS back-up service
- Month of Nov. - Build Access & Training, People Lists
- Jan. - Deploy Access & Training, People Lists? or hold until IAM Release 1
- ~FY14 Q3 (TBD) - IAM Release 1 & START Release for YaleConnect, Email alias, NetID PINs, full START service catalog?
...
- FY14 Allocation =$137,000
- Total budget estimate = approx. $220,000, July 2013 spend = approx. $38,800
- Ask for ROC = $83,000 additional
- Christine is going to ROC next week with timeline, budget request and resource allocations.
Risks / Issues
...
- Oracle Upgrade planned for Sept 21. We are currently testing START against patch (in a patched environment) and will be completed Aug. 2.
Discussion
Christine going to ROC next week with timeline, budget request and resource allocations
...
- - START tested in patched environment successful!
- Approved allocation for FY14 $137,100. Budget estimate is approx. $220,000. Increase due to backfill for technical resources for 4 months.
Discussion
o Jackie wants to be sure request takes into account everything that needs to happen based on today's meeting (not sure if this was meant to go here)
IAM Dependencies
...