- Oracle Upgrade planned for Sept 21. - START tested in patched environment successful!
- Approved allocation for FY14 $137,100. Budget estimate is approx. $220,000. Increase due to backfill for technical resources for 4 months.
Next Steps
Discussion
- Training for Telecom, Ethernet, Back-up during Oct. for Nov 1 release
- Access & Training, People Lists – deploy when ready or wait for IAM Release 1 (~March 2014)
- Communications to Operating Group
- Presentation of FY14 plan to ROC on 8/15
o Jackie wants to be sure request takes into account everything that needs to happen based on today's meeting (not sure if this was meant to go here)
IAM Dependencies
...