Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

  • Some progress since last meeting
  • Going to have Fruition do health check using existing virtual admin hoursto change the contract with Fred so we can do more things
  • Amy is working on the upgrade
  • Mandy will be working on testing-related stuff, eventually

David Backeberg:

  • Done:
    • Killed a series of defects.
    • Closed out several group / user changes from RTS queue
    • closed out a few requests from RTS queue
    • Killed a series of defects.
    • Heard that Bedework calendar request is no longer wanted. Marked several update sets as ignore. Updated Trello board. Updated HPALM.
    • D897; Determined that we are officially not going to advance the fixes.
    Next:
    • Going to yank Yanked validator off the Micro Tier form; it was never in the requirement; Bill West was trying to be consistent
    • Received an Expenditure code for the Microtier form, and embedded it into the form
  • Next:
    • Need to attack more incidents in the SN queue
    • Going to meet up about Allen about D916 today
    • Need to schedule a block of time with Fred, talk about the work he already did
  • Obstacles:
  • Backlog:

Tim:

  • Done:
    • Meeting up with David Logie after this meeting
    • Integration problem with Quickbase; need a new account
  • Next: 
    • Continuing to emphasize importance of CMDB stuff.
  • Backlog:

Hari:

  • Done:
    • Progress on defects, the pile is shrinking.
  • Next:
    • R1041, need more test cases, clarification from some expert on Change module.
    • R1109 hpc service 
  • Obstacles:
  • Backlog:

...