General Info

Scheduled for every 3 weeks to discuss the START replacement project

Call-In Info

  1. Dial 6-5777, (203) 436-5777 or (855) 925-3266. 
  2. Enter Meeting ID: 60612 and #.
  3. Speak your name, then enter #.

Roll Call

Name

Org

Present

Christine Costantino

PM, ITSM

(tick)

Wendy Battles

CM, ITS

(error)

Jane Livingston

Sponsor, ITS

(error)

Ronn Kolbash

Sponsor, SSC

(error)

Liz Burnell

Director, IAM

(error)

Adriene Radcliffe

Sponsor, ITSM

(tick)

Marc Ulan

Sr. Director, Business systems

(tick) (optional)

 

 

 

Agenda

Please come to the meeting on time & prepared

  1. Project Updates
  2. Review wireframes & prototype
  3. Financial Update
  4. Communications Update
  5. Review milestones for delivery
  6. Issues Concerns?

Documents

Discussion

Project Updates (Christine)

  • Carry-over project for FY14 is in the portfolio for the officers.
  • We're working closely with IAM team re: NETID PIN, YaleConnect, Email alias. For this project these will continue to be manual processes. The next project (eServices) and the next IAM proejct will convert these to automatic processes.

Review Wireframes & Prototype

Financial Update

  • Resource costs through Mar '13: $96,400 of $100,000. We will be over budget as of end of April.

Communications Update (Christine on behalf of Wendy)

  • Working on getting Focus groups scheduled for high-level users, ops managers for late April, early May.
  • The communications plan and stakeholder analysis has been vetted.
  • Will soon get started on the training plan.

Review milestones for delivery

  • Plan/Analyze - 3/28 (99% complete)
  • Design/Build/Test - 12/1 - 8/1
    • Currently in Design and Build phases for Telecom (Mobile device, Pagers, Telephone sets & lines), Ethernet, and Central Campus Backup requests.
    • Training - 8/1 - 9/30
  • Deploy & Warranty - 9/1 - 9/30

Issues/Concerns -

  •  