  • Current: 
    • Steering Committee Meeting tomorrow
    • Updating and adding to work plan
    • TOC presentation and change request form
    • Finalizing deliverables for Planning and Analyze gate - will task team members to pitch in as appropriate.

Wendy & Kathleen:

  • Done: org impact analysis
    • Org impact analysis
    • Draft of the text for email notifications
    • Inventory of email and calendaring services - finalizing inventory and processes - Exchange will be the only service to be part of this project; others will become part of the FY14 e-services project.
  • Current:
    • Will schedule a follow-up meeting with julieJulie Grant re: financial approval process.
    • next steps - focus groups - ops managers and high users, received some recommendations, susan wells, dickman, sandy stein - where to hold these meetings
    • gather names, and start coordinating for early april
    • Inventory of email and calendaring services - finalizing inventory and processes this week with email team - yaleconnect only
    • Working with Janet Jeddry re: notification text for financial approval process. - done
    • Will schedule a follow-up meeting with Julie Grant re: financial approval process

Next:

    • look at training audiences and plan
    • schedule som meeting

Kesha:

  • Done: pager use cases, walkthrough today, then david can send to fruition
  • drafvt ethrnet, end of week
  • Current:
    • Will send financial approval process, talk with julie. send to fruition
    • to schedule meeting with sandy and steve next week
  • Next: Either Pager use cases
  • Current:
    • Working on Ethernet request - hopes to finish this by end of the week
    • Will schedule meeting with Sandy Boutin and Steve Degroat next week re: backup
    • Walk-through with Jeff re: pagers today; then David can send this to fruition
  • Next:
    • Telephone sets and lines

BarbaraDavid:

  • Done: Done: work to fruition,
    • Current:
      • Meeting with campus backup, questions from Kesha
      • Answer NetID questions for Kesha

    David:

      • PTAEO work  - Fruition is working on phase 3
      of Current:
      • Finish Visio of 4.
      • Visio mockup for Pagers - done? - walkthrough then to fruition
      • Completing data loader
      • HMont?
      • Lead Admin label
      • David will ; walk-through today, then send to Fruition
    • Current:
      • Completed loading Ops Manager data
      • Change "Head" label to "Lead Admin"
      • Will send the financial approval info to Fruition
      • ess 
      • bill to refresh dev, d to move to testSplitting out requests from incidents  (My Tickets, My Requests)

    Next: Bill will refresh the Dev environment soon, David will need to move his development into Test before then.

    Bob:

    • Done: working Working with dave Dave and bill Bill re ess: ESS, new wireframes, wire frames - how to morph current ui UI to new uiUI
    • Current: Creating prototype for tickets and requests split out - by end of march.

    Liz:

    •  
    • March?

    Issues/Concerns: None