  1. Project Updates
  2. Wireframe Review
  3. Update on Financial Approval (Wendy)
  4. Validate Charter (sent to you via email)
  5. Review milestones for delivery

Documents

START Wireframes 2.1.ppt

PM000 - Project Charter START Replacement ITS050S_Feb2013.doc

Discussion

Project Updates :(Christine)

  • Roger Kennedy has joined the Office of the CIO as our portfolio manager
  • Almost finished with the Analyze phase
  • Currently in Design and Build phases for Telecom requests 
  • Planning to present the TOC for the change request next week 
  • Resource costs through Feb '13: $126,400 of $250,800 = 50.3%
  • Carry-over project for FY14 is in the portfolio for the officers