- Roger Kennedy has joined the Office of the CIO as our portfolio manager
- Almost finished with the Analyze phase
- Currently in Design and Build phases for Telecom requests
- Planning to present the TOC for the change request next week
- Resource costs through Feb '13: $126,400 of $250,800 = 50.3%
- Carry-over project for FY14 is in the portfolio for the officers
...
Update on Financial Approval (Wendy)
- Presentation to BOLT/OG
Validate Charter (sent to you via email, print out)
Review milestones for delivery
- Plan/Analyze - 2/30 (almost complete)
- Design/Build/Test - 12/1/2012 - 8/1/2013
- Currently in Design and Build phases for Telecom requests (Mobile device, Pagers, Telephone sets & lines)
Past Meetings