Name | Representing | Attended | Alternate Attendee |
---|---|---|---|
Adusumilli, Hari | ServiceNow QA |
|
|
Boeher, Cheryl | Problem Process | |
|
Chavira, Ricardo | Service Catalog/Request Process |
|
|
Ortale, Dorothy | Knowledge Process |
|
|
Kovacs, Mark | Incident Process |
|
|
Smith, Rick | Metrics/CSI Process |
|
|
Tiseo, Lou | Change Process |
|
|
Turnbull, Chloe | ServiceNow BA |
|
|
Valdes, Julio | Configuration Management Process | |
|
West, William | ServiceNow DEV |
|
|
Radcliffe, Adriene | ITSM Program | |
|
Costantino, Christine | START Replacement Project Manager | |
|
Nichols, Tim | CMDB Project Manager | |
|
MEETING NOTES
DISCUSSION
- Discussion items
- Reviewed release notes from Friday's (5/3/2013) release. No issues have been reported.
- Process Documents can be found here https://yale.box.com/s/petqgexpqg05npm6fma6
- Reviewed outstanding prioritization list. Added three items to the priority list (Items 6 - 8). Original prioritization remained the same, just new items were added to the bottom of the list. See below for the new prioritization.
- Going forward prioritization list will have columns to easily tell status of where in the item sits in the requirements/development/release process.
- The E-810 is in development.
- E-798 and E-715 are both signed off and ready for development.
- E-821 and E-630 are both in requirements gathering stages.
PRIORITIZED ITEMS AFTER MEETING
- E-810 - Metrics - Grant table access for Mirror42 so they can proceed with a proof of concept.
- STATUS: I believe these requirements are complete and signed off by everyone
- E-821 - Change - Update Change process and update ServiceNow to reflect those process changes. This will be done as part of the CMDB project.
- STATUS: Requirements/process work to start up again soon.
- E-798 - Incident - Implement customer satisfaction survey for Incident module
- STATUS: Requirements have been approved by Jim and committee and Chloe. Awaiting acceptance of requirements from Bill and Hari.
- E-715 - General System - Implement the 'Client (Unified)' field to include REQ, RITM and SCTASKS
- STATUS: Requirements approved by everyone I believe
- E-630 - Knowledge - Define a process for letting support teams know when there is new KB article that may be of interest to them.
- STATUS: Requirements gathering needs to begin for this process. Dorothy to work with teams to develop these requirements.
OUTSTANDING ACTION ITEMS
...
- Chloe to create a User Story/Use Case/Requirements Gathering format (from 4/22/13)
- Mark to schedule meeting with Chloe to review the Incident enhancement requests
- Chloe to add a status matrix to the prioritized items list
- DONE - Chloe to update HPQC and the Excel spreadsheet with today's updates.
.