Win

  1. Arts Calendar Launch

  2. Dev work on Manual Entry complete

  3. TAR development work completed

Needs input

  1. QA Carryover for FAS highly likely

  2. TAR Carryover possible pending UAT

  3. Arts Calendar Defects potentially reliant on meeting with Bedework team

Focus

  1. PeopleHub Integration for FAS

  2. Need to emphasize Developers to receive approval before adding issues to sprint

Goal

Progress

Notes

Arts Calendar - Launch!

COMPLETE

  • Launch was successful!

  • Michael, Nicolas and Luis are currently working to address bugs as they come in

TAR - Complete Dev Work for Job Description

COMPLETE

  • Dev work complete!

  • Stories may not be closed due to scheduling UAT

FAS - Complete Dev work for manual entry

ON TRACK

  • Currently, all outstanding manual entry pages have initial dev work complete

  • Significant QA work remaining

    • 6 stories are in testing and have associated defects

    • 8 stories are ready for testing

    • 9 stories awaiting UAT

  • PeopleHub Integration and Data Model update stories still in progress

FMP - UTIL Stories completed

ON TRACK

  • The stories have been created

  • Detailed description required for the body of all stories

  • Refinement required for stories not in this sprint

FMP - Server Updates

COMPLETE

Ops Dash - Process at least one alert from Everbridge

ON TRACK

Ops Dash - Initialize Theme

COMPLETE

Burndown Chart - Time Remaining