Win
Arts Calendar Launch
Dev work on Manual Entry complete
TAR development work completed
Needs input
QA Carryover for FAS highly likely
TAR Carryover possible pending UAT
Arts Calendar Defects potentially reliant on meeting with Bedework team
Ops Dash-Everbridge still in flight - working with external source means goal may be dependent on Everbridge
Focus
PeopleHub Integration for FAS
Need to emphasize Developers to receive approval before adding issues to sprint
Goal | Progress | Notes |
---|---|---|
Arts Calendar - Launch! | COMPLETE |
|
TAR - Complete Dev Work for Job Description | COMPLETE |
|
FAS - Complete Dev work for manual entry | ON TRACK |
|
FMP - UTIL Stories completed | ON TRACK |
|
FMP - Server Updates | COMPLETE | |
Ops Dash - Process at least one alert from Everbridge | ON TRACK |
|
Ops Dash - Initialize Theme | COMPLETE |
Burndown Chart - Time Remaining - https://yaleits.atlassian.net/jira/software/c/projects/CUS/boards/438/reports/burndown-chart?atlOrigin=eyJpIjoiNWIxMWExMzdmMjlkNDk0NjkyM2YwNTI2OTM4MTI3Y2IiLCJwIjoiaiJ9