Iteration Approach
Each iteration with some minor exception is 12 weeks.
Each iteration contains the following activities:
week |
SOW |
Stakeholder Analysis |
Requirements |
Design-Build |
Test |
Defect Repair |
Communications |
UAT |
Training |
Deployment |
Overlap to Next Sprint |
---|---|---|---|---|---|---|---|---|---|---|---|
1 |
x |
x |
x |
|
|
|
|
|
|
|
|
2 |
x |
x |
x |
x |
|
|
|
|
|
|
|
3 |
|
|
x |
x |
|
|
x |
|
|
|
|
4 |
|
|
|
x |
|
|
|
|
|
|
|
5 |
|
|
|
x |
x |
|
|
|
|
|
|
6 |
|
|
|
x |
x |
|
|
|
|
|
|
7 |
|
|
|
|
x |
x |
x |
|
|
|
|
8 |
|
|
|
|
x |
x |
|
|
|
|
|
9 |
|
|
|
|
|
x |
|
x |
|
|
|
10 |
|
|
|
|
|
x |
x |
x |
x |
x |
x |
11 |
|
|
|
|
|
|
x |
x |
x |
x |
x |
12 |
|
|
|
|
|
|
x |
|
x |
x |
x |
Business Services
The project scope will include mapping of 5 business services. Each of those business services will have integration work or import requirements:
Iteration |
|
|
|
|
---|---|---|---|---|
1 |
|
|
|
|
2 |
|
|
|
|
3 |
|
|
|
|
4 |
|
|
|
|
5 |
|
|
|
|