Comment: Migrated to Confluence 4.0

...

  • No change in priority of work items 
  • RC to work with Lou, Cheryl, et al., regarding request for additional resources
  • Nate to follow up with Rick & Chloe regarding ITSM work stream metrics (as part of request for additional resources)
  • Reminder to absent members: Please send a delegate in your place!

PRIORITIZED ITEMS AFTER MEETING

...

  1. Bill to add the following modules to the ServiceNow application in the CMDB:  Incident, Problem, Change, Request, Knowledge, Configuration (from 5/29)
  2. Ricardo and Christine to gather requirements and use cases for E-901 (from 5/29)
  3. Bill to make estimate on length of time it will take to do technical analysis/development for open items on the list (fill in last few) (from 6/24)
  4. Hari to make estimate on length of time it will take to do testing for open items on the list.  Use "Level of Effort - TEST" column in HPQC. See Chloe with questions. (from 6/24)
  5. All Process Owners review their items on the defect/enhancement list for items that can be removed (from 7/1)
  6. DONE - Chloe to update HPQC and the Excel spreadsheet with today's updates.
    1. https://yale.box.com/s/00ndty4qhdlwdpz15rvy

...