  1. Dial 6-5777, (203) 436-5777 or (855) 925-3266. 
  2. Enter Meeting ID: 60612 and #.
  3. Speak your name, then enter #.

Documents

Roll Call

Name

Org

Present

Christine Costantino

PM, ITSM

(tick)

Wendy Battles

CM, ITS

(tick) (error)

Jane Livingston

Sponsor, ITS

(error)

Ronn Kolbash

Sponsor, SSC

(tick) (error)

Liz Burnell

Director, IAM

(error)

Adriene Radcliffe

Sponsor, ITSM

(tick)

Marc Ulan

Sr. Director, Business systems

(error) (tick) (optional)

 

 

 

Agenda

Please come to the meeting on time & prepared

  1. Project Updates
  2. TOC presentation (4/4)
  3. Financial Update
  4. Communications Update
  5. Review milestones for delivery
  6. Issues Concerns?

Documents

...

START Wireframes 2.1.ppt

PM000 - Project Charter START Replacement ITS050S_Feb2013.doc

Discussion

Project Updates (Christine)

...

Discussion

Project Updates (Christine)

  • Carry-over project for FY14 is in the portfolio for the officers.th TIC
  • We're working closely with IAM team on NETID PIN and YaleConnect requests.
    • Add Risk for ~July release of Generate NETID PIN by IAM team. We may need to adjust the current START system.
  • Will schedule Plan and Analyze gate in the next week or so.

TOC Presentation (Christine) - see attached documents

  • Presented change request to the TOC on 4/4 - approved.
  • Concerns included timing of training (August) for Ops Managers, etc. in the professional schools. Wendy will work this into the training plan.
  • Karen Colburn-Murphy and Susan Munson volunteered to participate in the focus groups.

Financial Update

  • Resource costs through Mar '13: $126,400 of $250,800 = 50.3%
  • Carry-over project for FY14 is in the portfolio for the officers
  • START and IAM technical teams will be meeting next week.

Wireframe Review (Christine) - see attached document

Update on Financial Approval & Communications (Wendy)

  • Presentation to BOLT/OG
  • Follow-up meeting scheduled with Julie
  •  

Communications Update (Christine on behalf of Wendy)

  • Working on getting Focus groups - scheduled for high-level users, ops managers

Validate Charter (sent to you via email, print out)

  • Ronn reviewed the charter, nothing to modifyfor late April, early May.
  • The communications plan and stakeholder analysis has been vetted.
  • Will soon get started on the training plan.

Review milestones for delivery

  • Plan/Analyze - 23/30 28 (almost 99% complete)
  • Design/Build/Test - 12/1 - 8/1
    • Currently in Design and Build phases for Telecom requests (Mobile device, Pagers, Telephone sets & lines), Ethernet, and Central Campus Backup requests.
    • Training - 8/1 - 9/30
  • Deploy & Warranty - 9/1 - 9/30

Issues/Concerns -

  • Communication to HR (generalists about what we are doing and what will be changing) - Talk to Julie about bringing in Nancy Creel Gross (HR) as a stakeholder group
  • IAM projects - what are the updated timelines for IAM projects?Relation to Marc Ulan's portfolio - Igor Budyanski is the START developer/SME to archive the data when sunsetting. 