Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Status

Activity

Description

Duration

 (tick)

Identify release date

see Release Calendar

minutes

 

Schedule cloning

clone from prd to: pre, trn, and tst for after release; https://hi.service-now.com/

minutes

 

Schedule code review

this should happen after initial handover and before release

minutes

 (tick)

Submit change request

Open a build/test change request in https://yale.service-now.com/, assign to INF SN App Support

minutes

 

Start release document

Copy from template ServiceNow Release YYYY-MM-DD

minutes

 

Requirements freeze

Curate, then freeze requirements, providing estimates for each using estimator spreadsheet or equivalent

hours

 

Build phase work

Begin work in dev

days

 

Unit tests

Ensure all pushed to tst & unit tested

hours

 

Initial code freeze

Hand over initial requirements list for functional & QA validation in tst

minutes

 

Conduct code review

Shouldn't take long, just basic validation of approach and docs

hours

 

Defect fixes

Iterative follow-up work in dev, test for defect resolution

days

 

Finalize release

Identify changes & updates that are going/not going. Push to pre.

hours

 

Final code freeze

Hand over final requirements list for functional & QA validation, w/ regression, in pre

minutes

 

Go/no-go

Decide to push to production.

minutes

 

Production deployment

Push to prd.

hours

 

Production rollback

If applicable; follow ServiceNow Rollback Procedure.

hours

 

Notify stakeholders

send out email w/ summary status & link to release documentation, close out RFC and cancel clone requests, if rollback or no-go.

minutes

 

Target/Actuals

Deliver target/actuals using estimator spreadsheet or equivalent

hours

Change Control

CHG####### once you open a change, link it hereCHG0004332

Release Notes

https://yale.service-now.com/kb_view.do?sysparm_article=KB0000066

...