Iteration | Dates | Scope | Integrations | Objectives |
---|---|---|---|---|
1 | Aug- Sept | Planning Iterations | None | Develop Iterations and Scope |
2 | Sept - Oct - Nov | CFS and Contract Management | datacenter inventory apps? | Datacenter inventory, Contract relationships of end-to-end simple infrastructure business service |
3 | Dec | Berlin Upgrade | None | Pre-Requisite for Iteration 4 based on the following features: |
4 | Jan - Feb - March | Desktop Personal Productivity (with top 5 provider services) and Software Asset Management | BigFix | Reporting on asset inventory meta data, lifecycle, and software compliance and usage |
5 | April - May - June | ServiceNow, Classes v2 and Kronos | Quickbase | model cloud service, tie in application inventory, test process for bringing in new business services |
Deliverables for each Iteration
- Milestone Schedule
- Detailed Resource Plan
- ROM estimate for SOWs needed
- Communication and Training plans
- Recommended process changes based on CMDB data
- Functionality backlog or technical debt created during iteration