The project scope will include mapping of 5 business services. Each of those business services will have integration work or import requirements:
Iteration | Dates | Scope | Integrations | Objectives | ||||||||
---|---|---|---|---|---|---|---|---|---|---|---|---|
1 |
|
|
| Aug- Sept | Planning Iterations | None | Develop Iterations and Scope | |||||
2 |
| Sept - Oct - Nov | CFS and Contract Management |
| Datacenter inventory, Contract relationships of end-to-end simple infrastructure business service | |||||||
3 | Dec | Berlin Upgrade |
| None | Pre-Requisite for Iteration 4 | |||||||
4 |
|
|
|
| 5 |
|
|
| Jan - Feb - March | Desktop Productivity (with top 5 provider services) and Software Asset Management | BigFix | Reporting on asset inventory meta data, lifecycle, and software compliance and usage |
5 | April - May - June | ServiceNow, Classes v2 and Kronos | Quickbase | model cloud service, tie in application inventory, test process for bringing in new business services |