  1. Project Updates
  2. TOC presentation (4/4)
  3. Financial Update
  4. Communications Update
  5. Review milestones for delivery
  6. Issues Concerns?

Discussion

Project Updates (Christine)

...

  • Resource costs through Feb '13: $126,400 of $250,800 = 50.3%
  • Carry-over project for FY14 is in the portfolio for the officersSTART and IAM technical teams will be meeting .
  • We're working closely with IAM team on NETID PIN and YaleConnect requests.
  • Will schedule Plan and Analyze gate in the next week.

Wireframe Review TOC Presentation (Christine) - see attached document

Update on Financial Approval & Communications (Wendy)

...

documents

  • Presented change request to the TOC on 4/4 - approved
  • Concerns included timing of training (August) for Ops Managers, etc. in the professional schools. Wendy will

Financial Update

  • Resource costs through Mar '13: $126,400 of $250,800 = 50.3%
  •  

Communications Update (Christine on behalf of Wendy)

  • Working on getting Focus groups - scheduled for high-level users, ops managers

Validate Charter (sent to you via email, print out)

  • Ronn reviewed the charter, nothing to modifyfor late April, early May.
  • The communications plan and stakeholder analysis has been vetted.
  • Will soon get started on the training plan.

Review milestones for delivery

  • Plan/Analyze - 2/30 (almost complete)
  • Design/Build/Test - 12/1 - 8/1
    • Currently in Design and Build phases for Telecom requests (Mobile device, Pagers, Telephone sets & lines)
    • Training - 8/1 - 9/30
  • Deploy & Warranty - 9/1 - 9/30