  • Telecom & IT Requests
    • Training in October
    • Planned deployment Nov 1.
    • Release: Pagers, Telephone services, Ethernet connection, Mobile devices, ITS backup service (Central campus backup)
  • Access Requests & Training, People Lists
    • Policy review with Oracle Process Owners - Nancy
    • User interface & API to Oracle, SciQuest, Xpress Shipping
    • Training in November? Deploy in December? Decommission XTRAIN
  • Email & NetID PINs (YaleConnect, Email alias, NetID PINs)
    • Impact for Client Accts - Sept. release would require manual work (Avg. 450 requests/month) - Unacceptable.
    • Automation will become available with IAM solution (Release 1 ~FY14 Q3).
    •  
  • Oracle – move training to TMS, decommission XTRAIN, SciQuest, Xpress Shipping. Some manual work today will be included in new request process. Process Owners to review training requirements
  • People Lists (Analysis & Design phase) - Originally part of IAM project portfolio, solution not ready. Building with Oracle until IAM solution is ready.
  • START Replacement Training - Just-in-time, to coincide with release(s). To take place 4 weeks prior for big bang release

Project Milestones

  • SeptMonth of Oct. - Telecom & IT requests built
  • Sept 30 - Original START release date
  • Oct. - Access requests (XTRAIN) & People Lists built?
  • 4 weeks before release - TrainingApprover and fulfillment training
  • Nov. 1 - Deploy ITS service requests for pagers, telephone services, mobile devices, Ethernet connection and ITS back-up service
  • Month of Nov -
  •  
  •  
  • ~FY14 Q3 (TBD) - IAM Release 1 & START Release for YaleConnect, Email alias, NetID PINs, full START service catalog?

...