- Team Members
- What did you do last week?
- What are you doing this week?
- What obstacles are slowing/stopping progress?
- Do we have any issues or risks to discuss with the ITSM program committee?
- Other issues / concerns?
Documents
Discussion
Christine:
- Done
- attended Email Modernization mtg re: which email services should be part of this project.
- updated charter, schedule and resource plans; sent to Adriene for review
- re-scheduled TOC mtg on 3/7 for change request (scope & schedule)
- Current
- meeting with Bob & Jane re: wireframes
- meeting with Jay Fusco's team re: XTRAIN
- updating and adding to work plan
- writing go-in position for removing mobile device accessories - shop with business (Wendy, Kathleen)
- Next: TOC presentation and change request form
...