    • Presentation for Julie Grant yesterday went very well
    • Communications plan (including service owners) draft = 85% complete
  • Current:
    • Updating presentation to present to BOLT and operating group to 2/28 re: overall approach; mtgs to update presentation this week
    • Working on org impact analysis beginning tomorrow
    • Inventory of email and calendaring services - vetting this week with email team this week
  • General notes:
    • Training for Ops Managers will begin in August
    • Ops managers (TACs) will be engaged for feedback, Julie hasnit yet suggested Ops Managers to work with

Kesha:

  • Requirements for Ethernet, pagers, telephone sets and lines, documenting requirements
  • telephone Current:
    • Telephone sets and lines - half done, tomorrow meeting with Jeff and Alice
    • Ethernet meeting this week
    • Financial approval for telecom
    • & use cases
    for these

Barbara:

- people list as-is analysis in blueworksw, START maintain lists, mtg Thurs. - add Matt Pretka.

...