Versions Compared

Key

  • This line was added.
  • This line was removed.
  • Formatting was changed.

...

Goal

Progress

Notes

Arts Calendar - Launch!

Status
colourGreen
titleComplete

  • Launch was successful!

  • Michael, Nicolas and Luis are currently working to address bugs as they come in

TAR - Complete Dev Work for Job Description

Status
colourGreen
titleComplete

  • Dev work complete!

  • Stories may not be closed due to scheduling UAT

FAS - Complete Dev work for manual entry

Status
colourYellow
titleon track

  • Currently, all outstanding manual entry pages have initial dev work complete

  • Significant QA work remaining

    • 6 stories are in testing and have associated defects

    • 8 stories are ready for testing

    • 9 stories awaiting UAT

  • PeopleHub Integration and Data Model update stories still in progress

FMP - UTIL Stories completed

Status
colourYellow
titleon track

  • The stories have been created

  • Detailed description required for the body of all stories

  • Refinement required for stories not in this sprint

FMP - Server Updates

Status
colourGreen
titlecomplete

Ops Dash - Process at least one alert from Everbridge

Status
colourYellow
titleon track

  • Jesus made good progress and got necessary updates from Everbridge, but still working on completing the goal

Ops Dash - Initialize Theme

Status
colourGreen
titlecomplete

...