Goal

Progress

Notes

Arts Calendar - Launch!

Status
colourGreen
titleComplete

  • Launch was successful!

  • Michael, Nicolas and Luis are currently working to address bugs as they come in

TAR - Complete Dev Work for Job Description

Status
colourGreen
titleComplete

  • Dev work complete!

  • Stories may not be closed due to scheduling UAT

FAS - Complete Dev work for manual entry

Status
colourYellow
titleon track

  • Currently, all outstanding manual entry pages have initial dev work complete

  • Significant QA work remaining

    • 6 stories are in testing and have associated defects

    • 8 stories are ready for testing

    • 9 stories awaiting UAT

  • PeopleHub Integration and Data Model update stories still in progress

FMP - UTIL Stories completed

Status
colourYellow
titleon track

  • The stories have been created

  • Detailed description required for the body of all stories

  • Refinement required for stories not in this sprint

FMP - Server Updates

Status
colourGreen
titlecomplete

Ops Dash - Process at least one alert from Everbridge

Status
colourYellow
titleon track

Ops Dash - Initialize Theme

Status
colourGreen
titlecomplete

Burndown Chart - Time Remaining

...

- https://yaleits.atlassian.net/jira/software/c/projects/CUS/boards/438/reports/burndown-chart?atlOrigin=eyJpIjoiNWIxMWExMzdmMjlkNDk0NjkyM2YwNTI2OTM4MTI3Y2IiLCJwIjoiaiJ9

...