Sprint Goals
YSB: Complete Topic and Buildings Classification stories - Complete Not on schedule
YSB: Close all 4.2 tasks - Complete
FRMS: 3.0 Release - Complete
FAS: Ingest Release 1/16 - Complete
CEA: Finish Print View - INCOMPLETE
SDF: Close all Maintenance Tasks - INCOMPLETE
Arts Cal: Close all Maintenance Tasks - INCOMPLETE
FMP: FMS Med3 Upgraded - Complete
YSB: Complete Topic and Buildings Classification stories - Complete Not on schedule
Dev: Build classification Logic Public Safety https://yaleits.atlassian.net/browse/CUS-15027 - Complete Not on schedule
Several tasks created initially that were closed - significant rework to ticket needed.
QA Subtasks | Planned | Actual |
---|---|---|
None - Dev Only |
Defects | Planned | Actual |
---|---|---|
None - Dev Only |
CUS-15030 - Integrate Results Page Mockup https://yaleits.atlassian.net/browse/CUS-15030 - Complete Not on schedule
QA Subtasks | Planned | Actual |
---|---|---|
15m | 1h | |
1h | 1h 30m | |
30m | 30m | |
1h | 2h |
QA Subtask | Planned | Actual |
---|---|---|
https://yaleits.atlassian.net/browse/CUS-15643 - Currently Blocked due to Figma vs. Template Discussions | 6h 30m |
CUS-15028 - Dev: Topic filter logic plumbing, power, weather - https://yaleits.atlassian.net/browse/CUS-15028 Complete Not on schedule
Dev Subtask | Planned | Actual |
---|---|---|
2h | 2h 15m | |
2h | 4h 15m |
QA Subtasks | Planned | Actual |
---|---|---|
None - Dev Only |
Integrate Mockup for Advanced Search buttons and forms - https://yaleits.atlassian.net/browse/CUS-15029 Complete Not on schedule
Dev Subtask | Planned | Actual |
---|---|---|
1h | 2h | |
3h | 3h 30m | |
4h | 3h 15m |
QA Subtasks | Planned | Actual |
---|---|---|
30m | 30m | |
2h | 2h | |
30m | 30m | |
2h | ||
1h | ||
1h |
Defects - 4 valid, 2 related to figma v. template | Planned | Actual |
---|---|---|
1h 35 | ||
1h 45m | ||
1h 35m | ||
2h 20m |
CUS-15354 - Dev: Set new categories and sections to Incidents and Buildings - https://yaleits.atlassian.net/browse/CUS-15354 Complete
Dev Subtask | Planned | Actual |
---|---|---|
1h | 2h | |
3h | 3h 30m | |
4h | 3h 15m |
CUS-15316 - Dev: Build classification Start Tables for Logic - https://yaleits.atlassian.net/browse/CUS-15316 Complete
Dev Subtask | Planned | Actual |
---|---|---|
0m | 0m | |
4h | 0m | |
4h | 3h 30m |
QA Subtasks | Planned | Actual |
---|---|---|
None - Dev Only |
CUS-15332 - Dev: Build classification Logic - Atletics, Building, Campus Securityhttps://yaleits.atlassian.net/browse/CUS-15332 Complete
Dev Subtask | Planned | Actual |
---|---|---|
2h 30m | 2h 30m | |
2h 30m | 2h 30m | |
2h 30m | 30m | |
40m | 30m |
CUS-15337 - Dev: Build classification Logic - Facilities Ops, IT, Outageshttps://yaleits.atlassian.net/browse/CUS-15337 Complete
Dev Subtask | Planned | Actual |
---|---|---|
2h 30m | 45m | |
2h 30m | 45m | |
2h | 1h | |
45m | 30m |
CUS-15342 - Dev: Build classification Logic - Public Safety, Yale Alerts, Yale Health - https://yaleits.atlassian.net/browse/CUS-15342 Complete
Dev Subtask | Planned | Actual |
---|---|---|
2h 30m | 15m | |
2h 30m | 15m | |
2h 30m | 15m | |
40m | 30m |
CUS-15347 - Dev: Topic filter logic Construction Fire Alarm Flood - https://yaleits.atlassian.net/browse/CUS-15347 Complete
Dev Subtask | Planned | Actual |
---|---|---|
2h | 45m | |
2h | 45m | |
2h | 45m | |
30m | 30m |
CUS-15349 - Dev: Topic filter logic Grounds, It Outages, Odor - https://yaleits.atlassian.net/browse/CUS-15349 Complete Not on schedule
Dev Subtask | Planned | Actual |
---|---|---|
2h | 1h | |
2h | 1h | |
2h | 45m | |
30m | 30m |
CUS-15351 - Dev: Topic Merge All Topic Logics filters - https://yaleits.atlassian.net/browse/CUS-15351 Complete
Dev Subtask | Planned | Actual |
---|---|---|
2h | 1h | |
2h | 1h | |
2h | 45m | |
30m | 30m |
CUS-15661 - Advanced Search results page functionality - Headers Classification & Topics Deserealization - https://yaleits.atlassian.net/browse/CUS-15661 Not on schedule
Dev Subtask | Planned | Actual |
---|---|---|
3h | 2h | |
5h | 4h 30m | |
1h 30m | 1h |
CUS-15031 - Advanced Search results page functionality - https://yaleits.atlassian.net/browse/CUS-15031 Not on schedule
Dev Subtask | Planned | Actual |
---|---|---|
30m | 30m | |
7h | 5h | |
6h | 5h | |
8h | 6h 30m | |
2h | 0h | |
30m | 0h |
YSB: Close all 4.2 tasks - Complete
Dev work was started before in-depth project planning began - all stories were present across several sprints and many defects were not refined or added to a sprint.
https://yaleits.atlassian.net/browse/CUS-13587
Dev Subtask | Planned | Actual |
---|---|---|
2h | 2d 3h 45m | |
1d | 4d 4h 15m | |
2d | 1d 3h |
QA Subtasks | Planned | Actual |
---|---|---|
45m | 45m | |
4h | 4h | |
1h | 1h | |
5h | 5h |
Defects - 3 | Planned | Actual |
---|---|---|
https://yaleits.atlassian.net/browse/CUS-15418 - No QA Subtasks | 2h | 3h 45m |
https://yaleits.atlassian.net/browse/CUS-15421 - Not Refined, not added to sprint | 20m | 1h 15m |
https://yaleits.atlassian.net/browse/CUS-15424 - Not Refined, not added to sprint | 1h | 1h |
https://yaleits.atlassian.net/browse/CUS-13588 Complete
Defects - 4 | Planned | Actual |
---|---|---|
https://yaleits.atlassian.net/browse/CUS-15259 - Not Refined, not added to sprint | 1h 45m | 3h 15m |
https://yaleits.atlassian.net/browse/CUS-15360 - Not Refined, not added to sprint | 15m | 1h 30m |
https://yaleits.atlassian.net/browse/CUS-15384 - Not Refined, not added to sprint | 15m | 1h 30m |
https://yaleits.atlassian.net/browse/CUS-15391 - Not Refined, not added to sprint, no time logged for Dev | 15m | 15m |
https://yaleits.atlassian.net/browse/CUS-13589 Complete UAT Not on schedule
QA Subtasks | Planned | Actual |
---|---|---|
30m | 2h 30m | |
2h | 2h 30m | |
30m | 30m | |
2h | 5h | |
2h 30m | 30m |
Defects - 2 | Planned | Actual |
---|---|---|
https://yaleits.atlassian.net/browse/CUS-15380 - Not Refined, Not Added to Sprint, time not logged in dev task | 15m | 15m |
https://yaleits.atlassian.net/browse/CUS-15377
| 15m | 15m |
https://yaleits.atlassian.net/browse/CUS-13586
QA Subtasks | Planned | Actual |
---|---|---|
30m | 2h 30m | |
2h | 2h 30m | |
30m | 30m | |
2h | 5h | |
2h 30m | 30m |
What went well? What should we continue to do?
FRMS: 3.0 Release- Complete
CUS-14958 - Search all text in a grant - https://yaleits.atlassian.net/browse/CUS-14958
Dev Subtask | Planned | Actual |
---|---|---|
1d | 1d 2h 45m | |
1h | 2h | |
30m | 45m |
QA Subtasks | Planned | Actual |
---|---|---|
30m | 30m | |
1h 30m | 1h 30m | |
30m | 30m | |
2h | 2h | |
2h | 2h |
CUS-14959 - Add “Preparer” checkbox to user profiles - https://yaleits.atlassian.net/browse/CUS-14959
Dev Subtask | Planned | Actual |
---|---|---|
3h | 3h 15m | |
1h | 1h 45m | |
30m | 30m | |
1h | 1h | |
30m | 30m | |
CLOSED | CLOSED | |
CLOSED | CLOSED |
QA Subtasks | Planned | Actual |
---|---|---|
1h | 1h | |
4h | 0h | |
CLOSED | CLOSED | |
4h | 4h |
CUS-14961 - Add the IRES column to reports - https://yaleits.atlassian.net/browse/CUS-14961
Dev Subtask | Planned | Actual |
---|---|---|
4h | 3h 30m | |
1h | 1h 15m | |
30m | 1h |
QA Subtasks | Planned | Actual |
---|---|---|
1h | 0h | |
2h | 0h | |
CLOSED | CLOSED | |
3h | 3h | |
1h | 1h | |
30m | 30m |
CUS-15272 - Add name fields to User records - https://yaleits.atlassian.net/browse/CUS-15272
QA Subtasks | Planned | Actual |
---|---|---|
CLOSED | CLOSED | |
CLOSED | CLOSED | |
CLOSED | CLOSED | |
CLOSED | CLOSED |
CUS-15283 - Add names to current records - https://yaleits.atlassian.net/browse/CUS-15283
What went well? What should we continue to do?
FAS: Ingest Release 1/16 - Complete
CUS-11862 - Data ingest issue - https://yaleits.atlassian.net/browse/CUS-11862
Dev Subtask | Planned | Actual |
---|---|---|
https://yaleits.atlassian.net/browse/CUS-12178 https://yaleits.atlassian.net/browse/CUS-12178 | 7h 30m | 121h 45m |
3h | 21h | |
30m | 0m |
CUS-15038 - Add new process for data ingest - https://yaleits.atlassian.net/browse/CUS-15038
Dev Subtask | Planned | Actual |
---|---|---|
1d 4h | 4d 1h | |
30m | 0h | |
3h | 3h |
What went well? What should we continue to do?
CEA: Finish Print View - INCOMPLETE
CUS-14899 - PDF Export Truncating data - https://yaleits.atlassian.net/browse/CUS-14899
Closed, work continued on other tasks.
Dev Subtask | Planned | Actual |
---|---|---|
4h | 6h | |
4h | 19h | |
30m | 1h | |
30m | 1h |
QA Subtask | Planned | Actual |
---|---|---|
1h | 4h | |
CLOSED | CLOSED | |
20m | 1h | |
30m | 0m |
CUS-15400 - CEA - Create Printer friendly view - https://yaleits.atlassian.net/browse/CUS-15400
Dev Subtask | Planned | Actual |
---|---|---|
2h | 3h | |
4h | 8h | |
30m | 0m | |
30m | 30m |
QA Subtask | Planned | Actual |
---|---|---|
30m | 15m | |
2h | 30m | |
2h | TO DO |
Defects - 3 | Planned | Actual |
---|---|---|
5h 20m | TO DO - conversation in ticket | |
3h | 2h 15m | |
4h 45m | TO DO - conversation in ticket |
What can we do better next time?
SDF: Close all Maintenance Tasks- INCOMPLETE
CUS-14886 - SDF (AI MENTOR) Dev: Fix: Unlimited Records in Aggregates - https://yaleits.atlassian.net/browse/CUS-14886
Dev Subtask | Planned | Actual |
---|---|---|
1h | 2h | |
1h | 30m | |
40m | 40m | |
40m | 40m | |
2h | 30m | |
1h | 30m | |
40m | 40m | |
40m | 40m | |
1h | 1h | |
40m | 40m | |
1h | 2h 30m | |
30m | 30m |
CUS-14882 - SDF(AI Mentor) Fix: Avoid Registered Role - https://yaleits.atlassian.net/browse/CUS-14882
Dev Subtask | Planned | Actual |
---|---|---|
2h | 2h | |
30m | TO DO | |
1h | TO DO |
QA Subtask | Planned | Actual |
---|---|---|
1h | IN PROGRESS | |
0m | 30m | |
2h | TO DO |
CUS-14909 - SDF (AI Mentor) CSS in screen style - https://yaleits.atlassian.net/browse/CUS-14909
Dev Subtask | Planned | Actual |
---|---|---|
4h | 25h | |
1h | TO DO | |
1h | TO DO |
QA Subtask | Planned | Actual |
---|---|---|
1h | TO DO | |
2h | TO DO |
CUS-14813 - SDF (AI Mentor) Fix: Multiple server requests (Aggregates or actions) inside Client Actions - https://yaleits.atlassian.net/browse/CUS-14813
Dev Subtask | Planned | Actual |
---|---|---|
2h | 3h | |
2h | 2h | |
2h | 2h | |
2h | 2h | |
2h | 2h | |
2h | 2h | |
2h | 2h | |
2h | 2h | |
2h | 2h | |
30m | TO DO |
QA Subtask | Planned | Actual |
---|---|---|
1h | 0m | |
2h | 0m |
CUS-15420 - SDF (AI MENTOR) Dev: Fix: Unlimited Records in Aggregates Part 2 - https://yaleits.atlassian.net/browse/CUS-15420
Dev Subtask | Planned | Actual |
---|---|---|
40m | 40m | |
40m | 40m | |
40m | 40m | |
40m | 40m | |
40m | 40m | |
40m | 40m | |
40m | 30m | |
40m | 30m | |
40m | 30m | |
40m | 30m | |
30m | 30m |
What can we do better next time?
Arts Cal: Close all Maintenance Tasks- INCOMPLETE
CUS-14776 - Arts Calendar (AI Mentor) Server Requests in Client Events - https://yaleits.atlassian.net/browse/CUS-14776
Closed, significant time spent on issue deemed irrelevant
Dev Subtask | Planned | Actual |
---|---|---|
30m | 30m | |
16h | 34h 30m | |
30m | 30m |
QA Subtask | Planned | Actual |
---|---|---|
1h | 1h | |
1h | 1h |
CUS-14778 - Arts Calendar (AI Mentor) Remove Inline CSS style - https://yaleits.atlassian.net/browse/CUS-14778
Dev Subtask | Planned | Actual |
---|---|---|
30m | 30m | |
2h | 4h | |
30m | 0m |
QA Subtask | Planned | Actual |
---|---|---|
2h | 2h | |
2h | 2h |
What can we do better next time?
FMP: FMS Med3 Upgraded - Complete
What went well? What should we continue to do?
Issues In To-Do
What happened?